|
长距离深埋隧洞TBM拆机研究
|
Abstract:
本文结合新疆某隧洞工程施工实例,对长距离深埋隧洞TBM拆机方案提出了拆卸洞室前置法与“拆 + 埋”法,从地质、工程安全、投资、工期进行分析研究,最终采用“拆 + 埋”法实现TBM拆机,以期对长距离深埋隧洞TBM拆机施工提供借鉴,从而达到快速、安全、经济的目的。
Based on a construction example of a tunnel project in Xinjiang, this paper proposes the pre-demolition method and the “demolition + burying” method for the TBM dismantling plan of a long-distance deep-buried tunnel. The analysis and research are carried out from the perspective of geology, engineering safety, investment, and construction period. Finally, the “dismantling + burying” method is adopted to realize the TBM dismantling, in order to provide a reference for the TBM dismantling construction of long-distance deep-buried tunnels, so as to achieve the purpose of rapid, safe and economical.
[1] | 李世民. 大型敞开式TBM长大隧洞内无损拆机技术[J]. 云南水力发电, 2019, 35(5): 126-128, 135. |
[2] | 黄金光. TBM拆卸洞及拆机起重系统优化设计研究[J]. 隧道建设, 2017, 37(2): 242-249. |
[3] | 肖海晖, 郭荣伟. TBM洞内拆卸方案[J]. 山西建筑, 2010, 36(3): 362-363. |
[4] | 冯欢欢, 陈馈. 西秦岭隧道洞内拆机方案设计与探讨[J]. 铁道工程学报, 2016(3): 87-92. |
[5] | 宋卿. 双护盾TBM洞内拆机施工组织及方法[J]. 冶金丛刊, 2018(14): 251-252. |