%T 长距离深埋隧洞TBM拆机研究
Research on Dismantling of TBM in Long-Distance and Deep-Buried Tunnel
%A 马骋
%J Hans Journal of Civil Engineering
%P 356-360
%@ 2326-3466
%D 2021
%I Hans Publishing
%R 10.12677/HJCE.2021.104040
%X 本文结合新疆某隧洞工程施工实例,对长距离深埋隧洞TBM拆机方案提出了拆卸洞室前置法与“拆 + 埋”法,从地质、工程安全、投资、工期进行分析研究,最终采用“拆 + 埋”法实现TBM拆机,以期对长距离深埋隧洞TBM拆机施工提供借鉴,从而达到快速、安全、经济的目的。
Based on a construction example of a tunnel project in Xinjiang, this paper proposes the pre-demolition method and the “demolition + burying” method for the TBM dismantling plan of a long-distance deep-buried tunnel. The analysis and research are carried out from the perspective of geology, engineering safety, investment, and construction period. Finally, the “dismantling + burying” method is adopted to realize the TBM dismantling, in order to provide a reference for the TBM dismantling construction of long-distance deep-buried tunnels, so as to achieve the purpose of rapid, safe and economical.
%K TBM,拆机,方案比选,“拆 + 埋”法
TBM
%K Dismantling
%K Plan Comparison and Selection
%K “Dismantling + Burying” Method