Mechanical Response Analysis of the Pile Foundation of the Shield Undercutting Replacement Bridge

DOI: 10.4236/ojg.2026.161004, PP. 52-72

Keywords: Pile Buttressing Technique, Shield Tunnel Construction, Numerical Simulation, Bridge Pile Foundation, Underpassing

Full-Text   Cite this paper   Add to My Lib

Abstract:

As a typical representative of the application of urban underground space, subway lines inevitably conflict with the foundations of existing buildings (structures). In this paper, in order to solve the problem of cross conflict between the shield tunnel and the pile foundation of existing bridges, with the background of an actual buttressing project, the finite element method was used to establish a model of the buttressing pile foundation of a bridge under a shield tunnel. Then, numerical simulation analysis was carried out on the basis of the model of the buttressing pile foundation of existing bridges under the shield tunnel, which includes surface settlement, vertical displacement of the bridge surface, displacement of the original pile and static pile caused by shield tunnel construction of the right line of the tunnel. The changes of pile axial force and the stress response of the buttress beam are analyzed and discussed, and the following conclusions are obtained: Firstly, the peripile frictional resistance of the pile foundation has a certain inhibiting effect on the reduction of soil settlement due to the influence of tunnel construction. Secondly, the beams and cover beams can play a certain role in the deformation coordination during the construction process. Again, in the process of shield tunneling, under the influence of tunneling pressure and grouting pressure, the original piles and hydrostatic piles will produce certain bending deformation in space. Finally, in the process of shield driving, the soil above the tunnel will settle downward, which will lead to the generation of negative frictional resistance under the influence of the coordinated deformation of the bearing platform and the remaining pile.

References

[1]  Lv, J., Lin, D., Wu, W., Huang, J., Li, Z., Fu, H., et al. (2022) Mechanical Responses of Slurry Shield Underpassing Existing Bridge Piles in Upper-Soft and Lower-Hard Composite Strata. Buildings, 12, Article 1000.
https://doi.org/10.3390/buildings12071000
[2]  Zhang, J., Zhao, M., Liu, H. and Xu, X. (2013) Networked Characteristics of the Urban Rail Transit Networks. Physica A: Statistical Mechanics and its Applications, 392, 1538-1546.
https://doi.org/10.1016/j.physa.2012.11.036
[3]  Tang, R., Lin, B. and Liang, P. (2019) Safety Study on Direct Pile Cutting of Shield Underneath a Residential Building. Journal of Underground Space and Engineering, 15, 878-883.
[4]  Wei, G., Yang, B., Wu, H., et al. (2020) Research on Longitudinal Deformation of Existing Shield Tunnel Caused by Shield Tunneling. Chinese Journal of Under-ground Space and Engineering, 16, 1754-1762+1808.
[5]  Makarchian, M. and Poulos, H.G. (1996) Simplified Method for Design of Underpinning Piles. Journal of Geotechnical Engineering, 122, 745-751.
https://doi.org/10.1061/(asce)0733-9410(1996)122:9(745)
[6]  Jin, F., Xu, Q., Ma, Z., Ma, J. and Ming, J. (2012) Study on the Length of Excavation Exposure during Pile Replacement under Bridges. Journal of Underground Space Engineering, 8, 396-403.
[7]  Vynnykov, Y.L., Kharchenko, M.O. and Manzhalii, S.M. (2021) Reinforcement of a Deformed Structure on the Pile Foundation. IOP Conference Series: Materials Science and Engineering, 1021, Article 012030.
https://doi.org/10.1088/1757-899x/1021/1/012030
[8]  Zhao, X., Zhang, T., Liu, S., et al. (2022) Analysis of Shaped Bearing Pile Foundation Buttress Construction and Its Safety. Construction Technology (in Chinese and English) Magazine, 334-337.
[9]  Ma, L. and Wang, J. (2012) Technology of Pile Foundation Underpinning in Shield Tunnel of Xi’an Subway. Applied Mechanics and Materials, 204, 1445-1448.
https://doi.org/10.4028/www.scientific.net/amm.204-208.1445
[10]  Xu, Q., Zhu, H., Ma, X., et al. (2012) Study on the Replacement and Pile Removal Technology of Group Pile Foundation Underneath an Underpass Shield Tunnel Crossing a Bridge. Journal of Geotechnical Engineering, 34, 1217-1226.
[11]  Li, D., Qian, J., Wu, S., et al. (2012) Finite Element Analysis of Deformation of Existing Buttress Piles under Excavation. Journal of Geotechnical Engineering, 34, 238-242.
[12]  Deng, T., Guan, Z., Chen, K., et al. (2015) Simplified Calculation of Jacking Load in Active Buttressing of Bridge Pile Foundation. Geotechnics, 36, 3259-3267.
[13]  Zhang, C., Zhao, Y., Zhang, Z. and Zhu, B. (2021) Case Study of Underground Shield Tunnels in Interchange Piles Foundation Underpinning Construction. Applied Sciences, 11, 1611-1612.
https://doi.org/10.3390/app11041611
[14]  Cheng, P., Xu, Q., Li, G. and Li, X. (2018) Influence on High-Speed Railway Bridge Caused by Shield Tunneling in Sandy Pebble Stratum and Its Controlling Technologies. Transportation Research Congress 2016: Innovations in Transportation Research Infrastructure, Reston, 6-8 June 2016, 507-520.
https://doi.org/10.1061/9780784481240.052
[15]  Stulgis, R.P., Barry, B.E. and Harvey, Jr., F.S. (2004) Foundation Underpinning with Mini-Piles: “A First” in Guyana, South America. GeoSupport 2004, Orlando, 29 December 2004, 700-711.
https://doi.org/10.1061/40713(2004)15
[16]  Horpibulsuk, S., Kumpala, A. and Katkan, W. (2008) A Case History on Underpinning for a Distressed Building on Hard Residual Soil Underneath Non-Uniform Loose Sand. Soils and Foundations, 48, 267-285.
https://doi.org/10.3208/sandf.48.267
[17]  Ishimura, T., Metoki, M. and Shimizu, M. (2006) Development of Removed Pile Method with Cutting. Tunnelling and Underground Space Technology, 21, 411-412.
https://doi.org/10.1016/j.tust.2005.12.058
[18]  van Hasselt, D.R.S., Hentschel, V., Hutteman, M., Kaalberg, F.J., van Liebergen, J.C.G., Netzel, H., et al. (1999) Amsterdam’s North/South Metroline. Tunnelling and Underground Space Technology, 14, 191-210.
https://doi.org/10.1016/s0886-7798(99)00033-4
[19]  Iwasaki, Y., Watanabe, H., Fukuda, M., Hirata, A. and Hori, Y. (1994) Construction Control for Underpinning Piles and Their Behaviour. Géotechnique, 44, 681-689.
https://doi.org/10.1680/geot.1994.44.4.681
[20]  Yamaguchi, I., Yamazaki, I. and Kiritani, Y. (1998) Study of Ground-Tunnel Interactions of Four Shield Tunnels Driven in Close Proximity, in Relation to Design and Construction of Parallel Shield Tunnels. Tunnelling and Underground Space Technology, 13, 289-304.
https://doi.org/10.1016/s0886-7798(98)00063-7