An Object-Oriented Algorithm for Flexible Construction Scheduling with Automated Task Splitting

DOI: 10.4236/jbcpr.2026.141002, PP. 21-40

Keywords: Construction Scheduling, Project Scheduling, Precedence Diagram Method, PDM with Multiple Relationships, Activity Splitting, Partial Criticality, Object-Oriented Algorithm, Construction Management Software

Full-Text   Cite this paper   Add to My Lib

Abstract:

The Precedence Diagram Method (PDM) is widely used for modeling large and complex construction projects characterized by non-linear execution logic, overlapping activities, and multiple precedence constraints. Despite involving standardized and recurrent operations (e.g., formwork, reinforcement, concreting), construction schedules often exhibit highly complex logic that challenges traditional Critical Path Method (CPM) analysis. In particular, PDM networks with multiple relationships complicate critical path identification and float determination, while current commercial scheduling tools impose restrictive logic and limited support for activity splitting. This study proposes a novel object-oriented algorithm and a supporting software tool that integrates automated multi-activity splitting, unrestricted handling of precedence types, and segment-level criticality identification within a unified scheduling framework. The proposed approach transforms complex PDM networks into equivalent Finish-to-Start-based structures solvable using conventional forward and backward pass algorithms, while strictly preserving the original scheduling logic. Results demonstrate that the proposed method improves analytical transparency, scheduling flexibility, and precision in critical path and float analysis, including the identification of partially critical activity segments. The proposed framework provides project managers with a practical and scalable solution to optimize productivity and reduce project duration in complex construction scheduling scenarios.

References

[1]  Hajdu, M. (2019) Critical Path Analysis in Precedence Diagramming Method Schedules. Automation in Construction, 103, 192-202.
[2]  Andersson, N. and Christensen, K. (2007) Practical Implications of Location-Based Scheduling. Proceedings of the Conference Construction Management and Economics: Past, Present and Future, Reading, 16-18 July 2007, 1367-1376.
[3]  McDaniel, N. and Bahnmaier, W. (2001) Scheduling Guide for Program Managers. Department of Defense.
[4]  Wiest, J.D. (1981) Precedence Diagramming Method: Some Unusual Characteristics and Their Implications for Project Managers. Journal of Operations Management, 1, 121-130.
https://doi.org/10.1016/0272-6963(81)90015-2
[5]  Moder, J.J., Phillips, C.R. and Davis, E.W. (1983) Project Management with CPM, PERT and Precedence Diagramming. McGraw-Hill.
[6]  Kim, J. and Chi, S. (2021) Limitations of Commercial CPM Scheduling Tools in Representing Complex Construction Logic. Journal of Construction Engineering and Management, 147, Article ID: 04021044.
[7]  Hajdu, M. and Isaac, S. (2020) Extensions of the Precedence Diagramming Method: A Review and Analysis. Engineering, Construction and Architectural Management, 27, 1525-1544.
[8]  Lu, M. and Lam, H. (2009) Transform Schemes Applied on Non-Finish-to-Start Logical Relationships in Project Network Diagrams. Journal of Construction Engineering and Management, 135, 863-873.
https://doi.org/10.1061/(asce)co.1943-7862.0000062
[9]  Valls, V. and Lino, P. (2001) Criticality Analysis in Activity-on-Node Networks with Minimal Time Lags. Annals of Operations Research, 102, 17-37.
https://doi.org/10.1023/a:1010941729204
[10]  Valls, V., Martí, R. and Lino, P. (1996) A Heuristic Algorithm for Project Scheduling with Splitting Allowed. Journal of Heuristics, 2, 87-104.
https://doi.org/10.1007/bf00226294
[11]  Lowsley, S. and Linnett, P. (2006) About Criticality in Project Networks. International Journal of Project Management, 24, 37-49.
[12]  Hegazy, T. and Menesi, W. (2010) Critical Path Segments Scheduling Technique. Journal of Construction Engineering and Management, 136, 1078-1085.
https://doi.org/10.1061/(asce)co.1943-7862.0000212
[13]  Hegazy, T. and Menesi, W. (2012) Enhancing the Critical Path Segments Scheduling Technique for Project Control. Canadian Journal of Civil Engineering, 39, 968-977.
https://doi.org/10.1139/l2012-024
[14]  Francis, A. and Miresco, E. (2006) Discussion of “Critical Path Method with Multiple Calendars” by Kyunghwan Kim and Jesús M. De La Garza. Journal of Construction Engineering and Management, 132, 542-543.
https://doi.org/10.1061/(asce)0733-9364(2006)132:5(542)
[15]  Kim, K. and de la Garza, J.M. (2005) Critical Path Method with Multiple Calendars. Journal of Construction Engineering and Management, 131, 330-342.
https://doi.org/10.1061/(asce)0733-9364(2005)131:3(330)
[16]  Ponce de Leon, G. (2008) Project Planning Using Logic Diagramming Method. AACE International Transactions, PS.S05.1-PS.S05.6.
[17]  Plotnick, F.L. (2006) Relationship Diagramming Method (RDM). AACE International Transactions, PS.08.1-PS.08.10.
[18]  Hajdu, M., Skibniewski, M.J., Vanhoucke, M., Horvath, A. and Brilakis, I. (2016) How Many Types of Critical Activities Exist? A Conjecture in Need of Proof. Procedia Engineering, 164, 3-11.
https://doi.org/10.1016/j.proeng.2016.11.585
[19]  Moon, H., Kim, H., Kamat, V.R. and Kang, L. (2015) Bim-Based Construction Scheduling Method Using Optimization Theory for Reducing Activity Overlaps. Journal of Computing in Civil Engineering, 29, Article ID: 04014048.
https://doi.org/10.1061/(asce)cp.1943-5487.0000342
[20]  Choi, B., Lee, H., Park, M., Cho, Y.K. and Kim, H. (2014) Framework for Work-Space Planning Using Four-Dimensional BIM in Construction Projects. Journal of Construction Engineering and Management, 140, Article ID: 04014041.
https://doi.org/10.1061/(asce)co.1943-7862.0000885
[21]  Crandall, K. (1973) Project Planning with Precedence Lead/Lag Factors. Project Management Quarterly, 4, 18-27.
[22]  Fondahl, J.W. (1961) A Non-Computer Approach to the Critical Path Method for the Construction Industry. Technical Report No. 9, Stanford University.
[23]  Galloway, P.D. (2006) Survey of the Construction Industry Relative to the Use of CPM Scheduling for Construction Projects. Journal of Construction Engineering and Management, 132, 697-711.
https://doi.org/10.1061/(asce)0733-9364(2006)132:7(697)