应用统计过程控制图监控项目的工期和成本
Application of Statistical Progress Control Chart to Monitor Project Duration and Cost

DOI: 10.12677/SA.2022.111014, PP. 120-127

Keywords: EVM,EDM,ACUSUM控制图,成本,工期
EVM
, EDM, ACUSUM Control Chart, Cost, Duration

Full-Text   Cite this paper   Add to My Lib

Abstract:

挣值管理(Earned Value Management, EVM)和挣得工期管理(Earned Duration Management, EDM)是监控和分析项目成本和工期的强有力工具。EDM是Khamooshi和Golafshani (2014)引入仅利用时间指标来计算工期的方法,目前对于EVM和EDM与累积和(CUSUM)控制图相结合的方法还没有被研究。本文分别利用来自EVM的成本表现指标(Cost Performance Index, CPI)和来自EDM的工期表现指标(Duration Performance Index, DPI)来构造CUSUM统计量,考虑到传统的CUSUM控制图一般是监控在假定漂移大小的前提下的过程,通常取漂移量σ=|u1-u0|/2。在大多数实际的工艺设计中,预先确定漂移的确切大小是一件困难的事情。因而本文选用Sparks (2000)提出的自启动累积和(Adaptive CUSUM, ACUSUM)控制图和EDM与EVM来分别监控实际工程项目的工期和成本变化,以使得项目管理者及时采取纠正措施来确保项目在预算和计划工期内完成。实验结果表明ACUSUM控制图对于项目成本和工期的监控是很有潜力的。
Earned Value Management (EVM) and Earned Duration Management (EDM) are powerful tools for monitoring and analyzing project cost and duration. EDM is a method that uses only time indicators to calculate duration introduced by Khamooshi & Golafshani (2014). At present, the method of combining EVM and EDM with CUSUM control chart has not been studied. This paper uses Cost Performance Index (CPI) from EVM and Duration Performance Index (DPI) from EDM to construct CUSUM statistics, respectively. Considering that the traditional CUSUM control chart generally monitors the process on the premise of assuming the magnitude of drift, the drift is usually taken σ=|u1-u0|/2. In most practical process design, it is difficult to determine the exact size of drift in advance. Therefore, this paper selects the Adaptive CUSUM control chart proposed by Sparks (2000). EDM and EVM are used to monitor the duration and cost shifts of the actual project, respectively. So that the project manager can take corrective measures in time to ensure that the project is completed within the budget and planned duration. The experimental results show that ACUSUM control chart is promising for monitoring of project cost and duration.

References

[1]  Aliverdi, R., Naeni, L.M. and Salehipour, A. (2013) Monitoring Project Duration and Cost in a Construction Project by Applying Statistical Quality Control Charts. International Journal of Project Management, 31, 411-423.
https://doi.org/10.1016/j.ijproman.2012.08.005
[2]  Bancescu, M. (2016) Controlling Project Schedule Progress, Using Control Charts. Cybernetics and Systems, 47, 602-615.
https://doi.org/10.1080/01969722.2016.1211883
[3]  Votto, R., Ho, L.L. and Berssaneti, F. (2020) Applying and Assessing Performance of Earned Duration Management Control Charts for EPC Project Duration Monitoring. Journal of Construction Engineering and Management, 146, No. 3.
https://doi.org/10.1061/(ASCE)CO.1943-7862.0001765
[4]  Votto, R, Ho, L.L. and Berssaneti, F. (2020) Multivariate Control Charts Using Earned Value and Earned Duration Management Observations to Monitor Project Performance. Computers & Industrial Engineering, 148, Article ID: 106691.
https://doi.org/10.1016/j.cie.2020.106691
[5]  Vanhoucke, V.M. (2006) A Comparison of Different Project Duration Forecasting Methods Using Earned Value Metrics. International Journal of Project Management, 24, 289-302.
[6]  Anbari, F.T. (2004) Earned Value Project Management Method and Extensions. IEEE Engineering Management Review, 32, 97.
https://doi.org/10.1109/EMR.2004.25113
[7]  Khamooshi, H. and Golafshani, H. (2014) EDM: Earned Duration Management, a New Approach to Schedule Performance Management and Measurement. International Journal of Project Management, 32, 1019-1041.
https://doi.org/10.1016/j.ijproman.2013.11.002
[8]  王兆军, 邹长亮, 李忠华. 统计质量控制图理论与方法[M]. 北京: 科学出版社, 2013.
[9]  Sparks, R.S. (2000) CUSUM Charts for Signalling Varying Location Shifts. Journal of Quality Technology, 32, 157-171.
https://doi.org/10.1080/00224065.2000.11979987
[10]  Yeo, K.T. and Ning, J.H. (2002) Integrating Supply Chain and Critical Chain Concepts in Engineer-Procure-Construct (EPC) Projects. International Journal of Project Management, 20, 253-262.
https://doi.org/10.1016/S0263-7863(01)00021-7
[11]  Yeo, K.T. and Ning, J.H. (2006) Managing Uncertainty in Major Equipment Procurement in Engineering Projects. European Journal of Operational Research, 171, 123-134.
https://doi.org/10.1016/j.ejor.2004.06.036
[12]  Lucas, J.M. and Saccucci, M.S. (1990) Exponentially Weighted Moving Average Control Schemes: Properties and Enhancements. Technometrics, 32, 1-12.
https://doi.org/10.1080/00401706.1990.10484583