乐昌峡水库汛末提前蓄水优化调度研究
|
Abstract:
乐昌峡水库原设计从10月1日开始蓄水,导致水库蓄满率很低。本文根据水库蓄水调度控制线,计算蓄水期分期设计洪水和防洪控制水位,建立多目标水库优化蓄水调度模型,并采用NSGA-II算法求解。结果表明:在防洪限制水位的约束下,蓄水时间越提前,水库的综合利用效益越大。与原设计方案相比,8月1日和9月1日起蓄方案蓄水期发电量分别提高了21.62%和13.49%,蓄满率分别提高了10.40%和9.96%,多年平均蓄水量分别增加了4979和3647万m3。在确保防洪安全的前提下确定关键时间节点及对应水位,可为提前蓄水调度提供技术参考。
The designed impoundment scheme of Lechang reservoir was started in October 1, which results in a low impoundment efficiency. In this study, the seasonal design floods and flood control limited water level during the impounding period were calculated. Based on the reservoir impoundment operation lines, a multi-objective operation model was established and solved by the NSGA-II algorithm. Compared with the designed impoundment scheme, the advance impoundment scheme for August 1 (or September 1) can increase 21.62% (or 13.49%) power generation, 10.40% (or 9.96%) total impoundment efficiency, and 4979 (or 3647) million m3 water resources, respectively. Determining key time nodes and corresponding water levels can provide technical reference for advance impoundment operation on the premise of ensuring flood control safety.
[1] | 李海彬, 黄东, 练伟航, 刘画眉. 乐昌峡水库动库容特性及防洪优化调度[J]. 广东水利水电, 2013(6): 6-8+12.
LI Haibin, HUANG Dong, LIAN Weihang and LIU Huamei. Dynamic storage capacity characteristics and flood control optimal operation of Lechangxia Reservoir. Guangdong Water Resources and Hydropower, 2013(6): 6-8+12. (in Chinese) |
[2] | 刘心愿, 郭生练, 刘攀, 李响. 考虑综合利用要求的三峡水库提前蓄水方案[J]. 水科学进展, 2009, 20(6): 851-856.
LIU Xinyuan, GUO Shenglian, LIU Pan and LI Xiang. Scheme of impounding in advance for the Three Gorges Reservoir by considering the comprehensive utilization benefits. Advances in Water Science, 2009, 20(6): 851-856. (in Chinese) |
[3] | 李雨, 郭生练, 郭海晋, 张洪刚, 丁胜祥. 三峡水库提前蓄水的防洪风险与效益分析[J]. 长江科学院院报, 2013, 30(1): 8-14.
LI Yu, GUO Shenglian, GUO Haijin, ZHANG Honggang and DING Shengxiang. Flood control risk and benefit of impounding water in advance for the Three Gorges Reservoir. Journal of Yangtze River Scientific Research Institute, 2013, 30(1): 8-14. (in Chinese) |
[4] | 汪芸, 郭生练, 李天元. 丹江口水库提前蓄水方案[J]. 武汉大学学报(工学版), 2014, 47(4): 433-439.
WANG Yun, GUO Shenglian and LI Tianyuan. Study of scheme of impounding in advance for Danjiangkou reservoir. Engineering Journal of Wuhan University, 2014, 47(4): 433-439. (in Chinese) |
[5] | 陈柯兵, 郭生练, 何绍坤, 尹家波, 杨光. 基于月径流预报的三峡水库优化蓄水方案[J]. 武汉大学学报(工学版), 2018, 51(2): 112-117.
CHEN Kebing, GUO Shenglian, HE Shaokun, YIN Jiabo and YANG Guang. Optimal impounding operation of Three Gorges Reservoir based on monthly runoff forecasting. Engineering Journal of Wuhan University, 2018, 51(2): 112-117. (in Chi-nese) |
[6] | 何绍坤, 郭生练, 刘攀, 陈柯兵, 熊丰, 张剑亭. 金沙江梯级与三峡水库群联合蓄水优化调度[J]. 水力发电学报, 2019, 38(8): 27-36.
HE Shaokun, GUO Shenglian, LIU Pan, CHEN Kebing, XIONG Feng and ZHANG Jianting. Joint and optimal impoundment operation of Jinsha River’s cascade reservoirs and Three Gorges Reservoir. Journal of Hydroelectric Engineering, 2019, 38(8): 27-36. (in Chinese) |
[7] | 谢雨祚, 尹家波, 李千珣, 郭生练, 何绍坤, 熊丰, 何志鹏, 邓乐乐, 张文选, 温岩. 考虑生态流量的清江梯级水库优化调度研究[J]. 水资源研究, 2021, 10(1): 1-10.
XIE Yuzuo, YIN Jiabo, LI Qianxun, GUO Shenglian, HE Shaokun, XIONG Feng, HE Zhipeng, DENG Lele, ZHANG Wenxuan and WEN Yan. Optimal operation cascade reservoirs in the Qing River considering ecological flow. Journal of Water Resources Research, 2021, 10(1): 1-10. (in Chinese) |
[8] | 郭生练, 熊丰, 涂圣勤, 李娜, 张文选, 温岩. 清江梯级水库提前蓄水多目标联合优化调度[J]. 水资源研究, 2021, 10(2): 125-136.
GUO Shenglian, XIONG Feng, TU Shengqin, LI Na, ZHANG Wenxuan and WEN Yan. Multi-object early impound operation for cascade reservoirs in Qing river. Journal of Water Resources Research, 2021, 10(2): 125-136. (in Chinese) |