乐昌峡水库汛期运行水位动态控制研究
Dynamic Control of Operating Water Level in Flood Season at Lechangxia Reservoir

DOI: 10.12677/JWRR.2021.104040, PP. 371-380

Keywords: 水位,动态控制,预报预泄,风险控制,乐昌峡水库
Water Level
, Dynamic Control, Forecasting and Pre-Discharge, Risk Analysis, Lechangxia Reservoir

Full-Text   Cite this paper   Add to My Lib

Abstract:

乐昌峡水库为季调节水库,汛限水位为144.5 m,汛期调度可使用的库容仅0.18亿m3,造成水库大量弃水。考虑气象水文预报信息及其来水起涨过程的不确定性,建立乐昌峡水库预报预泄调度和风险分析模型,推求6 h和12 h预报信息相对应的汛期运行水位动态控制上限,分别为145.7 m和147.5 m。实现乐昌峡水库汛期运行水位动态控制,多年平均可增发电量1190万kW?h,减小弃水量5410万m3,经济社会效益显著。
The Lechangxia reservoir is seasonally regulated and affected by the flood limit water level of 144.5 m, and the adjustable storage capacity is only 18 million m3 which wastes flood resources in flood season. Considering the meteorological and hydrological forecasting information and the inflow uncertainty of rising process, a pre-discharge scheme and risk analysis model was established. Based on 6 h and 12 h inflow forecasts, the dynamic control upper bounds of water level in flood season were 145.7 m and 147.5 m, respectively. Compared with the designed scheme, the dynamic control of operating water level scheme can generate 11.90 million kW?h more hydropower and reduce 54.1 million m3 discharged water annually, which has significantly social and economic benefits.

References

[1]  郭生练, 钟逸轩, 吴旭树, 刘章君. 水库洪水概率预报和汛期运行水位动态控制[J]. 中国防汛抗旱, 2019, 29(6): 1-4. GUO Shenglian, ZHONG Yixuan, WU Xushu and LIU Zhangjun. Reservoir flood probability forecasting and dynamic control of water level during flood season. China Flood & Drought Management, 2019, 29(6): 1-4. (in Chinese)
[2]  刘攀, 郭生练, 李响, 陈炯宏, 李雨. 基于风险分析确定水库汛限水位动态控制约束域研究[J]. 水文, 2009, 29(4): 1-5. LIU Pan, GUO Shenglian, LI Xiang, CHEN Jionghong and LI Yu. Deriving the interval of reservoir dynamic flood control water level based on risk analysis. Journal of China Hydrology, 2009, 29(4): 1-5. (in Chinese)
[3]  李响, 郭生练, 刘攀, 万民, 刘心愿. 考虑入库洪水不确定性的三峡水库汛限水位动态控制域研究[J]. 四川大学学报(工程科学版), 2010, 42(3): 49-55. LI Xiang, GUO Shenglian, LIU Pan, WAN Min and LIU Xinyuan. The dynamic control bound of flood limited water level considering inflow uncertainty in Three Gorges Reservoir. Journal of Sichuan University (Engineering Science Edition), 2010, 42(3): 49-55. (in Chinese)
[4]  陈炯宏, 郭生练, 刘攀, 等. 梯级水库汛限水位联合运用和动态控制研究[J]. 水力发电学报, 2012, 31(6): 55-61. CHEN Jionghong, GUO Shenglian, LIU Pan, et al. Joint operation and dynamic control of flood limited water levels for cascade reservoirs. Journal of Hydroelectric Engineering, 2012, 31(6): 55-61. (in Chinese)
[5]  郭生练, 汪芸, 周研来, 尹家波. 丹江口水库洪水资源调控技术研究[J]. 水资源研究, 2015(4): 1-8. GUO Shenglian , WANG Yun, ZHOU Yanlai and YIN Jiabo. Optimal control of flood water resources for the Danjiangkou Reservoir. Journal of Water Resources Research, 2015(4): 1-8. (in Chinese)
[6]  任明磊, 何晓燕, 丁留谦, 王海军, 李辉, 谭亚男. 基于改进预泄能力约束法的水库汛限水位分期动态控制域确定及应用[J]. 中国水利水电科学研究院学报, 2018, 16(1): 16-22. REN Minglei, HE Xiaoyan, DING Liuqian, WANG Haijun, LI Hui and TAN Yanan. Research and application of staged dynamic controlling domain of limited reservoir water level in flood season based on the improved pre-discharge capacity constrained method. Journal of China Institute of Water Resources and Hydropower Research, 2018(1): 16-22. (in Chinese)
[7]  李海彬, 黄东, 练伟航, 刘画眉. 乐昌峡水库动库容特性及防洪优化调度[J]. 广东水利水电, 2013(6): 6-8+12. LI Haibin, HUANG Dong, LIAN Weihang and LIU Huamei. Dynamic storage capacity characteristics and flood control optimal operation of Lechangxia Reservoir. Guangdong Water Resources and Hydropower, 2013(6): 6-8+12. (in Chinese)

Full-Text

Contact Us

service@oalib.com

QQ:3279437679

WhatsApp +8615387084133