考虑物料配送的飞机移动生产线调度问题优化
|
Abstract:
摘要 以飞机移动生产线为实际背景,将作业装配过程调度抽象为资源受限项目调度问题并进行了扩展,引入物料配送与线边存储决策,以及相关能力约束等实际因素,建立了以装配总工期最小化为目标的数学模型。针对模型,设计了一种以遗传算法为框架的启发式算法,其中结合了解生成算法和局部优化搜索算法。在遗传算法较优的全局搜索能力下,通过SCRDS算法综合作业顺序、资源约束、配送能力、线边空间等因素,联合决策作业开始时间、物料配送时间和物料在线边空间的存储位置,提出了两作业间物料摆放位置调整的局部优化搜索算法,对作业开始时间和物料配送时间进行再优化,进一步缩短了装配总工期。利用标准算例库进行了数值实验,实验结果证明了模型与算法的有效性。
Abstract:This paper abstracted the scheduling of assembly process as a resource-constrained project scheduling problem in the background of aircraft moving assembly line, and decisions about material delivery and the storage of line-side material were introduced considering the capabilities, constraints and other practical factors. An integrating mathematical model with the objective of minimizing the makespan was established. A heuristic algorithm was proposed based on genetic algorithm framework, combining with solution generation algorithm and local optimization search algorithm. With the global searching advantages of genetic algorithm, a joint decision of start time, material delivery time and material storage position in line-side space for each job was made taking into account job sequence, resource constraints, delivery capability, line-side space and other factors through SCRDS algorithm. On this basis, a local optimization algorithm aiming at adjusting line-side material positions between two jobs was proposed to re-optimize the start time and material delivery time of jobs, which decreases the project duration further. Numerical experiments were carried out by using a standard example library and the results proved the validity of the model and algorithm.
[1] | CHALESHTARTI A S,SHADROKH S. Branch and bound algorithms for resource constrained project scheduling problem subject to cumulative resources[C]//International Conference on Information Management,Innovation Management and Industrial Engineering.Piscataway,NJ:IEEE Press,2011:147-152. |
[2] | BERTHOLD T,HEINZ S,LVBBECKE M E,et al.A constraint integer programming approach for resource-constrained project scheduling[M]//LODI A,MILANO M,TOTH P.Integration of AI and OR techniques in constraint programming for combinatorial optimization problems.Berlin:Springer,2010:313-317. |
[3] | BLAZEWICZ J,LENSTRA J K,KAN A H G R.Scheduling subject to resource constraints:Classification and complexity[J].Discrete Applied Mathematics,1983,5(1):11-24. |
[4] | TORMOS P,LOVA A.An efficient multi-pass heuristic for project scheduling with constrained resources[J].International Journal of Production Research,2003,41(5):1071-1086. |
[5] | BUKATA L,?ǔCHA P,HANZáLEK Z.Solving the resource constrained project scheduling problem using the parallel Tabu search designed for the CUDA platform[J].Journal of Parallel & Distributed Computing,2014,77(11):58-68. |
[6] | BOULEIMEN K,LECOCQ H.A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version[J].European Journal of Operational Research,2003,149(2):268-281. |
[7] | ALCARAZ J,MAROTO C.A robust genetic algorithm for resource allocation in project scheduling[J].Annals of Operations Research,2013,102(1):83-109. |
[8] | HARTMANN S.A self-adapting genetic algorithm for project scheduling under resource constraints[J].Naval Research Logistics,2002,49(5):433-448. |
[9] | KUMAR N,VIDYARTHI D P.A model for resource-constrained project scheduling using adaptive PSO[J].Soft Computing,2015,20(4):1565-1580. |
[10] | 王琰,陆志强.基于多重约束的飞机移动装配线作业调度优化[J].工业工程与管理,2011,16(6):115-120.WANG Y,LU Z Q.Job scheduling optimization of aircraft moving assembly line under multiple constraints[J].Industrial Engineering & Management,2011,16(6):115-120(in Chinese). |
[11] | 郑倩,奚立峰.飞机移动生产线作业调度问题的启发式算法[J].工业工程与管理,2015,20(2):116-121.ZHENG Q,XI L F.Heuristics for aircraft moving assembly line scheduling problem[J].Industrial Engineering & Management,2015,20(2):116-121(in Chinese). |
[12] | 葛茂根,刘明周,钱芳,等.基于JIT的多目标总装准时物料配送方法研究[J].中国机械工程,2011,22(23):2834-2838.GE M G,LIU M Z,QIAN F,et al.Research on multi-objective method on main assembly material delivery based on JIT[J].China Mechanical Engineering,2011,22(23):2834-2838(in Chinese). |
[13] | AGUIRRE A M,MéNDEZ C A,CASTRO P M.A hybrid scheduling approach for automated flowshops with material handling and time constraints[J].International Journal of Production Research,2014,52(9):2788-2806. |
[14] | FATHI M,ALVAREZ M J,MEHRABAN F H,et al.A multiobjective optimization algorithm to solve the part feeding problem in mixed-model assembly lines[J].Mathematical Problems in Engineering,2014,11(1):809-812. |
[15] | KHAYAT G E,LANGEVIN A,RIOPEL D.Integrated production and material handling scheduling using mathematical programming and constraint programming[J].European Journal of Operational Research,2006,175(3):1818-1832. |
[16] | MERKLE D,MIDDENDORF M,SCHMECK H.Ant colony optimization for resource-constrained project scheduling[J].IEEE Transactions on Evolutionary Computation,2002,6(4):333-346. |
[17] | FATHI M,RODRíGUEZ V,FONTES D B M M,et al.A modified particle swarm optimization algorithm to solve the part feeding problem at assembly lines[J].International Journal of Production Research,2016,54(3):1-16. |