External Quality Assurance of the Fehmarn Belt Fixed Link Business Case—Too Little, Too Late, and Too Unreliable

DOI: 10.4236/jfrm.2017.62011, PP. 126-149

Keywords: External Quality Assurance, Fehmarn Belt, New Construction Budgeting, High-Risk, Business Case

Full-Text   Cite this paper   Add to My Lib

Abstract:

The external quality assurance (EQA) of the Fehmarn Belt fixed link business case commissioned by the Danish Ministry of Transport is critically analyzed regarding the New Construction Budgeting requirements as well as common practical criteria. A time line of analyses, decisions and external quality assurance activities as well as external criticism is established as a basis for analyzing the completeness, timeliness and trustworthiness of the quality assurance. Information obtained per the Public Records Act is included. It is found that the external quality assurance was grossly incomplete with limited scopes and exclusion of major elements of the project. The overall financial performance and financial uncertainty analyses were not subject to external quality assurance at all. The bulk of external quality assurance was carried out only after the decision-to-build was made, preparatory construction activities initiated or major economic commitments made, thus jeopardizing the timeliness. The trustworthiness of the external quality assurance is limited for different reasons: bad timing of activities, lack of independence of consultancies, and controversial findings of opposing analyses. The external quality assurance is found to be too little, too late, and too unreliable. The status of the project as a high-risk business case is not improved by the external quality assurance.

References

[1]  Aigner, R. (2016). The Fehmarn Belt Duopoly—Can the Ferry Compete with a Tunnel? (13 p.). Discussion Paper 1539, Berlin: DIW.
[2]  Andersen, K. E. (2014). The Fehmarn Belt Fixed Link—Made in Denmark (107 p.). Copenhagen: Praxis.
[3]  Andersen, K. E. (2015). Analysis of New Traffic Forecasts for the Fehmarn Belt Fixed Link, 2014 (72 p.). Copenhagen: Praxis. (In Danish)
[4]  Berlingske Business (2007). Scandlines Sold for DKK 11.6 Billion. (In Danish)
[5]  Bredsdorff, M. (2015a). The Tax Payers Will Have to Pay Part of the Fehmarn Bill. IngeniØren, 2 October 2015, Based on Work by H. Schjær-Jacobsen. (In Danish)
[6]  Bredsdorff, M. (2015b). Large Uncertainty about Every Fourth Car in the Fehmarn Tunnel. IngeniØren, 20 November 2015. (In Danish)
[7]  BØrsen (2015). Fehmarn-Shock: New Minister of Transport Misses DKK 4 Billion. 29 June 2015. (In Danish)
[8]  BØrsen (2017a). Scandlines Warms up to Fehmarn Showdown by Venturing Billions. 14 March 2017. (In Danish)
[9]  BØrsen (2017b). Criticism from Shipping Company Can Take Femern A/S to Court. 14 March 2017. (In Danish)
[10]  COWI (2004). Economic Assessment of a Fixed Link across the Fehmarn Belt— Summary Report (20 p.). 29 March 2004, Commissioned by the Danish Ministry of Transport.
[11]  COWI (2011). Customer Survey of Fehmarn Belt (26 p.). 16 February 2011.
[12]  COWI (2015a). External Quality Assurance of the Updated Traffic Forecast of the Fehmarn Belt Project (8 p.). First Draft of Work Program 20 April 2015, Last Draft 21 May 2015. (In Danish)
[13]  COWI (2015b). External Quality Assurance of the Updated Traffic Prognosis of the Fehmarn Belt Project (39 p.). Ministry of Transport, 10 November 2015. (In Danish)
[14]  Danish Parliament (2008). Binding Political Agreement between the Government (the Liberal Party and the Conservative Party), the Social Democrats, the Socialist People’s Party and the Social Liberal Party about a Fehmarn Belt Fixed Link (2 p.). 2 September 2008. (In Danish)
[15]  Danish Parliament (2009a). Binding Political Agreement between the Government (the Liberal Party and the Conservative Party), the Social Democrats, the Socialist People’s Party, the Social Liberal Party and Liberal Alliance: A Green Transport Policy (30 p.). 29 January 2009. (In Danish)
[16]  Danish Parliament (2009b). Planning of a Fixed Link crossing Fehmarn Belt with Connecting Land Works in Denmark. Planning Act No. 285. April 2009. (In Danish, also Available in English Translation)
[17]  Danish Parliament (2011). Act No. 149 (6 p.). Passed by the Finance Committee on 23 June 2011. (In Danish)
[18]  Danish Parliament (2013). Act No. 97 (4 p.). Passed by the Finance Committee on 20 March 2013, Confidential until 26 February 2015. (In Danish)
[19]  Danish Parliament (2015). Construction and Operation of a Fixed Link crossing Fehmarn Belt with Connecting Land Works in Denmark. Construction Act L141, Proposed on 25 February 2015 and Passed on 28 April 2015. (In Danish)
[20]  Danish Parliament (2016). Binding Political Agreement between the Government (the Liberal Party), the Social Democrats, Danish People’s Party, Liberal Alliance, the Social Liberal Party, the Socialist People’s Party and the Conservative Party concerning: The Continued Process of the Fehmarn Belt Fixed Link (3 p.). 4 March 2016. (In Danish)
[21]  Deloitte (2012). External Quality Assurance—E47 South Motorway SakskØbing - RØdbyhavn (29 p.). 8 June 2012, Commissioned by the Danish Ministry of Transport. (In Danish)
[22]  Deloitte (2016). Scandlines RØdby-Puttgarden: Review of KPMG Report Dated 24 January 2016 (34 p.). 24 June 2016. Commissioned by Scandlines.
[23]  DIW Econ GmbH (2015a). Comments to New Traffic Forecast for the Fehmarn Belt Fixed Link (14 p.). 20 January 2015. Commissioned by Scandlines. (In German)
[24]  DIW Econ GmbH (2015b). Investigation of the Recent Cost-Benefit Analysis of the Fehmarn Belt Fixed Link (19 p.). 19 February 2015. Commissioned by Scandlines. (In Danish)
[25]  DIW Econ GmbH (2015c). How Robust Are the Financial Analyses of the Fehmarn Belt Fixed Link? (76 p.). Commissioned by Scandlines. (In German).
[26]  Ernst & Young (2016). External Quality Assurance of the Fehmarnbelt Fixed Link Including Danish Land Works (69 p.). February 2016. Commissioned by the Danish Ministry of Transport and Building. (In Danish)
[27]  FDJV—Fehmarn Development Joint Venture (2002). Finances and Organization (156 p.). June 2002. (In Danish, originally in English)
[28]  Femern A/S (2003). Financial Analysis, February 2003 (20 p.). March 2003.
[29]  Femern A/S (2008). Financial Analysis (27 p.). September 2008. (In Danish)
[30]  Femern A/S (2010a). Construction Cost Estimate of a Cable Sustained Bridge—Comparison with the Planning Act (6 p.). 1 November 2010. (In Danish)
[31]  Femern A/S (2010b). Construction Cost Estimate of an Immersed Tunnel—Comparison with the Planning Act (6 p.). 1 November 2010. (In Danish)
[32]  Femern A/S (2010c). Consolidated Construction Cost Estimate of the Fehmarn Belt Fixed Link (8 p.). 1 November 2010.
[33]  Femern A/S (2011a). Backing of Immersed Tunnel, News Release. 21 February 2011. (In Danish)
[34]  Femern A/S (2011b). Traffic across the Great Belt between Zealand and Germany (2 p.). 21 April 2011. (In Danish)
[35]  Femern A/S (2011c). Nomination of RØdbyhavn as Production Site (6 p.). 25 May 2011. (In Danish)
[36]  Femern A/S (2011d). Consolidated Construction Estimates of the Fehmarn Belt Fixed Link (9 p.). 24 August 2011. (In Danish)
[37]  Femern A/S (2012). Time Schedule for the Fehmarn Belt Project (5 p.). 17 April 2012. (In Danish)
[38]  Femern A/S (2013). German Plan Approval Documents for the Fehmarn Belt Fixed Link. 1 October 2013. (In German)
http://femern.com/en/Tunnel/Milestones-for-the-project/Approval-process-in-Germany/The-German-plan-approval-procedure
[39]  Femern A/S (2014a). Traffic Forecast for a Fixed Link Crossing the Fehmarn Belt (74 p.). November 2014. (In Danish)
[40]  Femern A/S (2014b). Financial Analysis of the Fehmarnbelt Fixed Link Including Danish Land Works (56 p.). November 2014. (In Danish)
[41]  Femern A/S (2015a). Analysis of Fehmarn Forecast Based on Misinterpretation (8 p.). 16 January 2015. (In Danish)
[42]  Femern A/S (2015b). Status of Construction Budget for the Fixed Link across the Fehmarnbelt (3 p.). February 2015. (In Danish)
[43]  Femern A/S (2015c). What Is the Status of the Work in Femern A/S with the Tunnel Crossing Fehmarn Belt? News Release, 26 February 2015. (In Danish)
[44]  Femern A/S (2015d). Note: Road Users on the Great Belt en route between Zealand and Germany (2 p.). 21 April 2015. (In Danish)
[45]  Femern A/S (2016a). Financial Analysis of the Fehmarnbelt Fixed Link Including Danish Land Works (74 p.). 3 February 2016.
[46]  Femern A/S (2016b). Memo-Financial Analysis for the Fehmarnbelt Project: Assumptions and Results February 2016 (3 p.). 10 February 2016.
[47]  Femern A/S (2016c). Fehmarn Belt Tunnel Contractors Appointed. 3 April 2016. (In Danish)
[48]  Femern A/S (2016d). Femern A/S Signs Conditional Contracts with the Prequalified Construction Consortia Concerning the Four Large Tunnel Contracts. Press Release, 30 May 2016. (In Danish)
[49]  Femern A/S (2016e). Revised Plan Approval Documents for the Fehmarn Belt Fixed Link. 13 June 2016. (In German)
http://pfu.femern.com/
[50]  Femern A/S (2016f). Work in Progress, Status Report from the Ministry of Transport in Schleswig-Holstein Regarding the German Approval (4 p.). Memo to the Transport and Building Committee of the Danish Parliament Appendix No. 83, 15 November 2016. (In Danish)
[51]  Femern A/S (2017a). Femern A/S Delivers Answers to Germany. Press Release, 15 February 2017. (In Danish)
[52]  Femern A/S (2017b).
http://femern.com/en
[53]  Femern A/S (2017c). The Economy of the Fehmarn Belt Project (2 p.). 27 February 2017. (In Danish)
[54]  Femern A/S (2017d). Femern A/S Signs Contracts with Engineering Consultants. News Release, 17 March 2017.
[55]  FTC—Fehmarn Belt Traffic Consortium (1999). Fehmarn Belt Traffic Demand Study— Final Report (350 p.). January 1999.
[56]  FTC—Fehmarn Belt Traffic Consortium (2003). Fehmarn Belt Forecast 2002—Final Report (150 p.). 1 April 2003.
[57]  IngeniØren (2016a). Fehmarn Surprise: The Commuters in Eastern Denmark Now Get a Railroad Worth DKK 7.5 Billion. 4 March 2016. (In Danish)
[58]  IngeniØren (2016b). COWI Is the Big Winner of the Fehmarn Invitation to Tender. 4 March 2016. (In Danish)
[59]  IngeniØren (2016c). Political Feint: Denmark Spends DKK 13 Billion on the Fehmarn Belt Fixed Link before German Approval. 11 March 2016. (In Danish)
[60]  IngeniØren (2016d). Top-Lawyers: The Danish Fehmarn Decision Is Based on Fortune Telling. 21 March 2016. (In Danish)
[61]  IngeniØren (2016e). Ministry: That’s Why Today’s Traffic Crossing Fehmarn Belt Means Nothing for the Tunnel. Five Questions to the Ministry of Transport from Journalist Frede Vestergaard, Weekend Avisen, 31 March 2016. (In Danish)
[62]  Intraplan/BVU—Intraplan Consult GmbH and BVU Beratergruppe GmbH (2014a). Fehmarnbelt Forecasts 2014—Update of the FTC-Study of 2002 (196 p.). November 2014.
[63]  Intraplan/BVU—Intraplan Consult GmbH and BVU Beratergruppe GmbH (2014b). Fehmarnbelt Forecasts 2014—Update of the FTC-Study of 2002, Annex (156 p.). November 2014.
[64]  Intraplan/BVU—Intraplan Consult GmbH and BVU Beratergruppe GmbH (2015a). Addendum to the Fehmarnbelt Forecasts 2014—Update of the FTC-Study of 2002 Referring to Additional Data and Statements Provided by Scandlines in January 2015 (3 p.). February 2015.
[65]  Intraplan/BVU—Intraplan Consult GmbH and BVU Beratergruppe GmbH (2015b). Fehmarnbelt Forecasts 2014—Update of the FTC-Study of 2002—Treatment of the Great Belt in the Forecast (2 p.).
[66]  Jespersen, P. H. (2007). Road Freight Transport across Fehmarn Belt Fixed Link (7 p.). Presented at Traffic Days, Aalborg University, August 2007.
[67]  KPMG (2012). Quality Assurance of Railroad Constructions in Connection with the Fehmarn Belt Fixed Link (74 p.). Commissioned by the Ministry of Transport. (In Danish)
[68]  KPMG (2016). Business Analyses of the Ferry Link RØdby-Puttgarden (76 p.). 24 January 2016. Confidential 14 January 2016 edition published 14 March 2016 after leakage to German journalist. Commissioned by the Ministry of Transport and Building. (In Danish)
[69]  Lorentzen, K. P. (2015). Quotation from Speech in the Danish Parliament on the Occasion of the First Readings of L141, Folketingstidende, 18 March 2015. (In Danish)
http://www.folketingstidende.dk/RIpdf/samling/20141/forhandlinger/ M65/20141_M65_helemoedet.pdf#nameddest=L141
[70]  Rasmussen, I. L. (2015). Fehmarn Is the Worst Investment in the Danish History. Feature Article, IngeniØren, 9 March 2015. (In Danish)
[71]  Schjær-Jacobsen, H. (2015a). Financial Uncertainty of Fehmarn Belt Tunnel Is Systematically under Estimated (2 p.). Communication to the Danish Ministry of Transport and Members of the Commission of Transport and Buildings, Danish Parliament, Including Response from Femern A/S, 2 March 2015. (In Danish)
[72]  Schjær-Jacobsen, H. (2015b). The Minister Neglects the Serious Criticism of Fehmarn. Discussion Article, BØrsen, 26 November 2015. (In Danish)
[73]  Schjær-Jacobsen, H. (2016a). The Fehmarn Fixed Link Is a Financial High Risk Project. Feature Article, BØrsen, 13 January 2016. (In Danish)
[74]  Schjær-Jacobsen, H. (2016b). Construction and Operation of the Fehmarn Belt Immersed Tunnel Is a High Risk Business Case. In R. W. GrubbstrÖm, & H. H. Hinterhuber (Eds.), Pre-Prints of the 19th International Working Seminar on Production Economics (Vol. 1, pp. 367-378). Innsbruck.
[75]  Schjær-Jacobsen, H. (2016c). Revisiting Financial Uncertainty of the Fehmarn Belt Business Case (5 p.). Presented at Traffic Days 2016, Denmark: Aalborg University.
[76]  Schjær-Jacobsen, H. (2016d). Financial Uncertainty of the Fehmarn Belt Fixed Link (p. 56). Invited Paper Presented at the Concept Symposium: Governing the Front-End of Major Projects, Symposium Program, Stavanger: The Norwegian Ministry of Finance and the Norwegian University of Science and Technology, Sola Strand Hotel.
[77]  Schjær-Jacobsen, H. (2017a). Construction and Operation of the Fehmarn Belt Immersed Tunnel Is a High-Risk Business Case. Journal of Financial Risk Management, 6, 1-15.
[78]  Schjær-Jacobsen, H. (2017b). External Quality Assurance of the Fehmarn Belt Fixed Link Business Case - Too Little, Too Late, and Too Unreliable (24 p.). Internal Report, Version 1.5, RD&I Consulting, 18 March 2017.
[79]  State Memorandum (2000). The Danish German Decision on the Further Development of a Fixed Link across Fehmarn Belt (1 p.). 6 December 2000.
[80]  State Memorandum (2004). Joint Memorandum Concerning Cooperation about Further Development of the Fehmarn Belt Fixed Link between the Ministries of Transport of Germany and Denmark (3 p.). 23 June 2004. (In German and Danish)
[81]  State Memorandum (2007). Memorandum of Understanding Concerning a Fixed Link Crossing Fehmarn Belt between the Federal Republic of Germany and the Kingdom of Denmark (2 p.). 29 June 2007. (In Danish and German)
[82]  State Treaty (2008). Treaty between the Kingdom of Denmark and the Federal Republic of Germany on a Fixed Link across the Fehmarnbelt (16 p.). 3 September 2008. (In Danish and German)
[83]  S&B—Sund & Bælt Holding A/S (2015). Estimate of Foreign Passages 2009-2013 across the Great Belt (2 p.). 5 May 2015. (In Danish)
[84]  S&B—Sund & Bælt Holding A/S (2016). Project Proposal: Analysis of International Traffic on the Great Belt and Transfer to Fehmarn (6 p.). 20 January 2016.
[85]  S&B—Sund & Bælt Holding A/S (2017a).
http://sundogbælt.dk/en/frontpage/
[86]  S&B—Sund & Bælt Holding A/S (2017b). Answer to the Third Request of Access to Public Records Regarding EQA of Road Traffic Transfer from the Great Belt. 17 March 2017. (In Danish)
[87]  TRM—Danish Ministry of Transport (1999). The Fehmarn Belt Fixed Link—Economic Investigations (70 p.). August 1999. (In Danish)
[88]  TRM—Danish Ministry of Transport (2003). Financial Analysis, Traffic Forecast and Analysis of Railway Payment, Summary Report (82 p.). March 2003. (In Danish)
[89]  TRM—Danish Ministry of Transport (2004). Fixed Link across Fehmarnbelt—Financial Analysis (30 p.). June 2004.
[90]  TRM—Danish Ministry of Transport (2006a). Act No. 16 on New Construction Budgeting, Information to the Finance Committee (3 p.). 24 October 2006.
[91]  TRM—Danish Ministry of Transport (2006b). Fehmarn Belt—An Overview (15 p.). 19 December 2006. (In Danish)
[92]  TRM—Danish Ministry of Transport (2010a). New Construction Budgeting—Main Memorandum (45 p.). 24 August 2009, Revised 10 October 2010. (In Danish)
[93]  TRM—Danish Ministry of Transport (2010b). Terms of Reference for External Quality Assurance of the Basis for Decision Making at Level 1 (7 p.). 1 September 2010. (In Danish)
[94]  TRM—Danish Ministry of Transport (2011a). Terms of Reference for External Quality Assurance of the Basis for Decision Making at Level 2 (10 p.). 17 May 2011. (In Danish)
[95]  TRM—Danish Ministry of Transport (2011b). Production of Standard Elements for the Fehmarn Belt Immersed Tunnel Will Be Located in RØdbyhavn. Press Release, 1 June 2011. (In Danish)
[96]  TRM—Danish Ministry of Transport (2015a). Note: “Due Diligence” of Reserves and Risk Distribution (2 p.). 1. October 2015. (In Danish)
[97]  TRM—Danish Ministry of Transport (2015b). Answers to Questions from H. Schjær-Jacobsen Concerning Application of New Construction Budgeting to the Fehmarn Belt Fixed Link Project, E-Mail Exchange, 11 November 2015 - 25 February 2016. (In Danish)
[98]  TRM—Danish Ministry of Transport (2015c). Traffic Forecast Gives a Realistic Estimate on Road Traffic on the Fehmarn Belt Fixed Link. Press Release, 12 November 2015. (In Danish)
[99]  TRM—Danish Ministry of Transport (2015d). Request of Analysis of Potential Road Traffic Transfer from the Great Belt to Fehmarn Belt Fixed Link. E-Mail to Sund & Bælt Holding A/S, 12 November 2015. (In Danish)
[100]  TRM—Danish Ministry of Transport (2016a). Political Agreement about the Fehmarn Belt Project. News Release, 4 March 2016. (In Danish)
[101]  TRM—Danish Ministry of Transport (2016b). Exchange of Letters between Scandlines and the Ministry of Transport Concerning Confidential EQA Report, KPMG (9 p.). 10 March-18 March 2016. (In Danish)
[102]  TRM—Danish Ministry of Transport (2016c). German Delay of Environmental Approval of Fehmarn Belt Fixed Link. News Release, 12 December 2016. (In Danish)
[103]  TRM—Danish Ministry of Transport (2017a). Status of Construction and Building Projects—Second Half-Year 2016 (119 p.). (In Danish)
[104]  TRM—Danish Ministry of Transport (2017b). Letter to the Federal Minister of Transport. 16 February 2017. (Unauthorized Danish Translation)
[105]  Vieregg-RÖssler GmbH (2008). Expert Report on the Traffic Forecasts and Cost Calculations of the Proposed Fixed Fehmarnbelt Link (55 p.). Munich, January 2008. Commissioned by NABU.