电网技术  2013 

含高渗透率间歇性电源的电网规划方案优选方法

, PP. 2129-2135

Keywords: 电网规划方案,高渗透率,间歇性电源,优选,指标体系,DEMANTEL,网络分析法,逼近理想点法

Full-Text   Cite this paper   Add to My Lib

Abstract:

根据含高渗透率间歇性电源电网的特点,提出了一种该类型电网规划方案的优选方法。构建了包含电压稳定、频率稳定、充裕性、安全稳定性、间歇性电源接入容量和经济性等指标的评价指标体系。基于决策实行与评价实验室(decisionmakingtrailandevaluationlaboratory,DEMANTEL)法对传统网络分析法(analyticnetworkprocess,ANP)进行改进,并采用改进的网络分析法获取指标间相对权重。同时基于绝对正负理想点理论和投影型贴近度方法对传统逼近理想点(techniquefororderpreferencebysimilaritytoidealsolution,TOPSIS)法进行改进,在得到指标权重的基础上利用改进TOPSIS法生成各规划方案的整体排序,从而选出最优方案,最后给出算例证明了所提方法的有效性。

References

[1]  聂宏展,聂耸,乔怡,等.基于主成分分析法的输电网规划方案综合决策[J].电网技术,2010,34(6):134-138.Nie Hongzhan,Nie Song,Qiao Yi,et al.Comprehensive decision-making of alternative transmission network planning based on principal component analysis[J].Power System Technology,2010,34(6):134-138(in Chinese).
[2]  聂宏展,吕盼,乔怡,等.基于熵权法的输电网规划方案模糊综合评价[J].电网技术,2009,33(11):60-64.Nie Hongzhan,Lü Pan,Qiao Yi,et al.Comprehensive fuzzy evaluation for transmission network planning scheme based in entropy weight method[J].Power System Technology,2009,33(11):60-64(in Chinese).
[3]  余贻鑫,周金辉,秦超.基于价值的含大规模风电电力规划评估[J].天津大学学报,2011,44(11):941-947.Yu Yixin,Zhou Jinhui,Qin Chao.Value-based evaluation of power system planning alternatives with large-scale wind power[J].Journal of Tianjin University,2011,44(11):941-947(in Chinese).
[4]  杨琦,马世英,宋云亭,等.分布式电源规划方案综合评判方法[J].电网技术,2012,36(2):212-216.Yang Qi,Ma Shiying,Song Yunting,et al.Comprehensive evaluation of distributed generation planning scheme[J].Power System Technology,2012,36(2):212-216(in Chinese).
[5]  Bresesti P.Power system planning under uncertainty conditions, criteria for transmission network flexibility evaluation[C]//Power Tech Conference Proceedings.Bologna:IEEE,2003:803-808.
[6]  刘念,马丽,朱铁铭.计及抗灾能力和地区特点的配电网规划方案综合评价[J].电网技术,2012,36(5):219-225.Liu Nian,Ma Li,Zhu Tieming.Synthetical assessment on distribution network planning scheme considering anti-disaster ability and regional characteristics[J].Power System Technology,2012,36(5):219-225(in Chinese).
[7]  汪隆君,王钢.基于动态安全域与埃奇沃斯级数的电力系统暂态稳定概率评估[J].中国电机工程学报,2011,31(1):52-58.Wang Longjun Wang Gang.Probabilistic assessment if transient stability based on dynamic security region and Edgeworth series[J].Proceeding of the CSEE,2011,31(1):52-58(in Chinese).
[8]  Ana Roxana Ciupuliga,Madeleine Gibescu,Engbert Pelgrum,et al.Round-the-year security analysis with large-scale wind power integration[J].IEEE Trans on Sustainable Energy,2012,3(1):85-93.
[9]  王勇,韩学山,丁颖,等.基于马尔科夫链的电力系统运行可靠性快速评估[J].电网技术,2013,37(2):405-410.Wang Yong,Han Xueshan,Ding Ying,et al.Markov chain-Based rapid assessment on operational reliability of power grid[J].Power System Technology,2013,37(2):405-410(in Chinese).
[10]  Kerin U.Dynamic security indication in power systems with large amount of renewanles[C]//PowerEnergy Society General Meeting. San Diego,USA:IEEE,2012:1-6.
[11]  Kaur N.Evaluation of customer interruption cost for reliability planning of power systems in developing economies[C]//International Conference on Probabilistic Methods applied to Power Systems.Ames,IA:IEEE,2004:752-755.
[12]  孙强,葛旭波,刘林,等.智能电网多属性网络层次组合评价法及其应用研究[J].电网技术,2012,36(10):49-54.Sun Qiang,Ge Xubo,Liu Lin,et al.Multi-attribute network process comprehensive evaluation method for smart grid and its application[J].Power System Technology,2012,36(10):49-54(in Chinese).
[13]  罗志猛,周建中,张勇传,等.应用网络分析法的发电企业运营绩效综合评价[J].电网技术,2010,34(9):42-47.Luo Zhimeng,Zhou Jianzhong,Zhang Yongchuan,et al.Comprehensive evaluation of operational performance for power generation enterprises by analytic network process method[J].Power System Technology,2010,34(9):42-47(in Chinese).
[14]  李纳纳.ANP内部依赖矩阵构造方法的改进及其在项目评标中的应用[D].(长春:吉林大学),2010.
[15]  方爱丽,高齐圣,张嗣瀛.网络化DEMANTEL方法在产业经济系统分析中的应用[J].数学的实践与认识,2009,39(5):78-83.Fang Aili,Gao Qisheng,Zhang Siying.Application of network DEMATEL method in industry economic system analysis[J].Mathematics in Practice and Theory,2009,39(5):78-83(in Chinese).
[16]  胡元潮,阮羚,阮江军,等.基于改进逼近理想点法的变电站智能化改造评估[J].电网技术,2012,36(10):42-48.Hu Yuanchao,Ruan Ling,Ruan Jiangjun,et al.Evaluation on intelligent renovation of substations based on improved TOPSIS[J].Power System Technology,2012,36(10):42-48(in Chinese).
[17]  陆伟锋,唐厚兴.关于多属性决策TOPSIS方法的一种综合改进[J].统计与决策,2012,19(7):38-40.Lu Weifeng Tang Houxing.Comprehensive improvement of multi-attribute decision-making TOPSIS method[J].Statistics and Decision,2012,19(7):38-40(in Chinese).
[18]  胡永宏.(对TOPSIS法用于综合评价的改进[J].数学的实践与认识),2002,32(4):572-575.Hu Yonghong.The improved method for TOPSIS in comprehensive evaluation[J].Mathematics in Practice and Theory,2002,32(4):572-575(in Chinese).