电网技术  2015 

以减少电网弃风为目标的风电与抽水蓄能协调运行

DOI: 10.13335/j.1000-3673.pst.2015.09.015, PP. 2472-2477

Keywords: 风电,弃风,抽水蓄能,协调运行,混合整数规划

Full-Text   Cite this paper   Add to My Lib

Abstract:

由于风电出力特性及电力系统运行约束等限制,电网接入大量风电时将会导致大量弃风。对风电与抽水蓄能协调运行以减少电网弃风的方式进行研究,在分析导致电网弃风的主要因素的基础上,充分考虑抽水蓄能的运行特性,以电网弃风最小为优化目标,建立风电和抽水蓄能协调运行的混合整数规划模型。基于实际电力系统的风电出力和负荷数据,在IEEE30节点系统中对风电与抽水蓄能协调运行方式进行模拟。结果表明,所提出的优化模型能有效地模拟风电与抽水蓄能协调运行的过程;风电与抽水蓄能的协调运行方式对减少电网弃风具有显著的作用;对具有一定风电装机容量的电网,存在最优的抽水蓄能容量与之协调运行,使得电网弃风最小。

References

[1]  孙元章,吴俊,李国杰.风力发电对电力系统的影响[J].电网技术,2007,31(20):55-62.Sun Yuanzhang,Wu Jun,Li Guojie.Influence research of wind power generation on power system[J].Power System Technology,2007,31(20):55-62(in Chinese).
[2]  张宁,周天睿,段长刚,等.大规模风电场接入对电力系统调峰的影响[J].电网技术,2010,34(1):152-158.Zhang Ning,Zhou Tianrui,Duan Changgang,et al.Impact of large-scale wind farm connecting with power grid on peak load regulation demand[J].Power System Technology,2010,34(1):152-158(in Chinese).
[3]  张丽英,叶廷路,辛耀中,等.大规模风电接入电网的相关问题及措施[J].中国电机工程学报,2010,30(25):1-9.Zhang Liying,Ye Tinglu,Xin Yaozhong,et al.Problems and measures of power grid accommodating large scale wind power[J].Proceedings of the CSEE,2010,30(25):1-9(in Chinese).
[4]  Fink S,Mudd C,Poter K,et al.Wind energy curtailment case studies[R].Colorado:National Renewable Energy Laboratory,2009.
[5]  Rogers J,Fink S,Poter K.Examples of wind energy curtailment practices[R].Colorado:Exeter Associates,2010.
[6]  吕泉,王伟,韩水,等.基于调峰能力分析的电网弃风情况评估方法[J].电网技术,2013,37(7):1887-1894.Lv Quan,Wang Wei,Han Shui,et al.A new evaluation method for wind power curtailment based on analysis of system regulation capability[J].Power System Technology,2013,37(7):1887-1894(in Chinese).
[7]  国家电力监管委员会.风电、光伏发电情况监管报告[R].北京:国家电力监管委员会,2011.
[8]  刘新东,方科,陈焕远,等.利用合理弃风提高大规模风电消纳能力的理论研究[J].电力系统保护与控制,2012,40(6):35-39.Liu Xindong,Fang Ke,Chen Huanyuan,et al.Research on rational wind power casting theory for large-scale wind power integration improvement[J].Power System Protection and Control,2012,40(6):35-39(in Chinese).
[9]  Burke D J,O’ malley M J.Factors influencing wind energy curtailment[J].IEEE Trans on Sustainable Energy,2011,2(2):185-193.
[10]  Faias S,Sousa J,Castro R.Embedded energy storage systems in the power grid for renewable energy sources integration[M].Rijeka,Croatia:INTECH Open Access Publisher,2009:63-88.
[11]  Gill S,Ault G W,Kockar I.The optimal operation of energy storage in a wind power curtailment scheme[C]//Proceedings of 2012 IEEE Power and Energy Society General Meeting.San Diego,California,USA:IEEE,2012:1-8.
[12]  胡泽春,丁华杰,孔涛.风电-抽水蓄能联合日运行优化调度模型[J].电力系统自动化,2012,36(2):36-41.Hu Zechun,Ding Huajie,Kong Tao.A joint daily operational optimization model for wind power and pumped storage plant[J].Automation of Electric Power Systems,2012,36(2):36-41(in Chinese).
[13]  徐飞,陈磊,金和平,等.抽水蓄能电站与风电的联合优化运行建模及应用分析[J].电力系统自动化,2013,37(1):149-154.Xu Fei,Chen Lei,Jin Heping,et al.Modeling and application analysis of optimal joint operation of pumped storage power station and wind power[J].Automation of Electric Power Systems,2013,37(1):149-154(in Chinese).
[14]  Gaicia-Gonzelze J,de la Muela R M R,Santos L M,et al.Stochastic joint optimization of wind generation and pumped storage units in an electricity market[J].IEEE Transactions on Power Systems,2008,23(2):460-468.
[15]  Tuohy A,O’ malley M.Impact of pumped storage on power systems with increasing wind penetration[C]//Proceedings of 2009 IEEE Power and Energy Society General Meeting.Canada:IEEE,2009:1-8.
[16]  张鹏,刘继春,吕林,等.基于风蓄协调的节能调度方法[J].电力系统保护与控制,2011,39(2):29-34.Zhang Peng,Liu Jichun,Lü Lin,et al.The energy-saving dispatch based on the coordination between pumped storage hydro and wind energy[J].Power System Protection and Control,2011,39(2):29-34(in Chinese).
[17]  Loganathan G,Moore C.Operating policy for a pumped storage hydropower system[C]//Watershed Management and Operations Management 2000.Fort Collins,Colorado,USA:ASCE,2000:1-10.
[18]  梅祖彦.抽水蓄能发电技术[M].北京:机械工业出版社,2000:4-5.
[19]  Vorarlberger Illwerke AG.Hydropower plant KopsII[EB/OL].2008[2014-11-20].http://www.kopswerk2.at.
[20]  Grotenburg K,Koch F,Erlich I,et al.Modeling and dynamic simulation of variable speed pump storage unit incorporated into the German Electric Power System[J].EPE Trondheim,2001,8(1):67-77.
[21]  IBM.IBM ILOG CPLEX optimization studio user’s guide[EB/OL].2013[2014-12-03].ftp://public.dhe.ibm.com/software/websphere/ilog/ docs/optimization/cplex/ps_usrmancplex.pdf.
[22]  BPA.Wind generation & total load in the BPA balancing authority[EB/OL].2013[2014-10-12].http://transmission.bpa.gov/ Operations/ Wind/ default.aspx.