金属露天矿生产计划优化算法的改进

DOI: 10.3969/j.issn.1005-3026.2014.10.028, PP. 1492-1495

Keywords: 露天矿,生产规划,优化,锥体排除法,动态规划

Full-Text   Cite this paper   Add to My Lib

Abstract:

针对露天矿生产计划优化中使用锥体排除法产生地质最优开采体序列时,不考虑锥体之间重叠部分对相应锥体的平均品位影响的问题,提出了改进的锥体排除算法.该算法在锥体排除过程中,重新确定了锥体的空间搜索逻辑,同时重新计算锥体数组中受品位最低锥体影响的各锥体的平均品位并重新排序.把新算法产生的地质最优开采体序列作为状态变量建立动态排序模型,对所有可行的路径进行评价,得出NPV最大的路径作为最优开采方案.实例应用表明,在相同技术经济条件下,改进后的优化算法无论是生产能力稳定性还是最终净现值都明显优于原算法,其中NPV提高了105%.

References

[1]  [1]Crawford J T,Davey R K.Case study in openpit limit analysis[C]//Computer Methods for the 80s in the Mineral Industry.New York,1979:311-318.
[2]  Belobraidich W.Computer assisted long range mine planning practice at ray mine division—Kennecott copper corporation[C]//Computer Methods for the 80’s in the Mineral Industry.New York,1979:349-357.
[3]  Savage C J,Preller A H.Computerized mine planning system at Rio Tinto Mineral,S.A.(Spain)[C]//Proceedings of the 19th Application of Computers and Operations Research in the Mineral Industry.Universal Park,1987:441-456.
[4]  Halatchev R A.A model of discounted profit variation of open pit production sequencing optimization[C]//Proceedings of the 32nd International Symposium on the Application of Computers and Operations Research in the Mineral Industry.Tucson,2005:315-323.
[5]  Ramazan S.The new fundamental tree algorithm for production scheduling of open pit mines[J].European Journal of Operations Research,2006,177(2):1153-1166.
[6]  Armstrong M,Galli A.A new approach to flexible open pit optimization and scheduling[C]//Proceedings of the 35th International Symposium of Application of Computers and Operations Research in the Minerals Industry.Wollongong,2011:253-263.
[7]  Menabde M,Froyland G,Stone P.Mining schedule optimization for conditionally simulated orebodies[C]//Proceedings of the International Symposium on Orebody Modeling and Strategic Mine Planning:Uncertainty and Risk Management.Perth,2004:379-383.
[8]  Armstrong M,Galli A,Ndiaye A A.A case study on the impact of hedging against foreign exchange risk and energy price risk[C]//Proceedings of Orebody Modeling and Strategic Mine Planning.Dimitrakopoulos,2009:95-99.
[9]  Gholamnejad J,Osanloo M.Incorporation of ore grade uncertainty into the push back design process[J].The Journal of the Southern African Institute of Mining and Metallurgy,2007,107:177-185.
[10]  Grobler F,Elkington T,Rendu J M.Robust decision makingapplication to mine planning under price uncertainty[C]//Proceedings of the 35th International Symposium of Application of Computers and Operations Research in the Minerals Industry.Wollongong,2011:59-66.一位数()
[11]  二位数()(上接第1481页)3结论1) 在以乙硫氮为捕收剂的条件下,SGX的添加使黄铜矿的回收率有一定幅度的增加,而对方铅矿有强的抑制作用.通过人工混合矿浮选试验可知,在pH=6,SGX质量浓度为19 g/L时,黄铜矿和方铅矿的分离效果较好,精矿中铜的质量分数和回收率分别为2966