Allen E H,Stuart R B,Wiedman T E.No light in August:power system restoration following the 2003 North American blackout[J].IEEE Power and Energy Magazine,2014,12(1):24-33.
[2]
薛禹胜,肖世杰.综合防御高风险的小概率事件:对日本相继天灾引发大停电及核泄漏事件的思考[J].电力系统自动化,2011,35(8):1-11.Xue Yusheng,Xiao Shijie.Comprehensively defending high risk events with low probability[J].Automation of Electric Power Systems,2011,35(8):1-11(in Chinese).
[3]
汤涌,卜广全,易俊.印度“7.30”、“7.31”大停电事故分析及启示[J].中国电机工程学报,2012,32(25):1-5.Tang Yong,Bu Guangquan,Yi Jun.Analysis and lessons of the blackout in Indian power grid on July 30 and 31,2012[J].Proceedings of the CSEE,2012,32(25):1-5(in Chinese).
[4]
Fink L H,Liou K L,Liu C C.From generic restoration actions to specific restoration strategies[J].IEEE Trans. on Power Systems,1995,10(2):745-751.
[5]
Adibi M M,Fink L H.Power system restoration planning[J].IEEE Trans. on Power Systems,1994,9(1):22-28.
[6]
Ancona J J.A framework for power system restoration following a major power failure[J].IEEE Trans. on Power Systems,1995,10(3):1480-1485.
[7]
周云海,闵勇.恢复控制中的系统重构优化算法研究[J].中国电机工程学报,2003,23(4):67-70.Zhou Yunhai,Min Yong.Optimal algorithm for system reconstruction[J].Proceedings of the CSEE,2003,23(4):67-70(in Chinese).
[8]
刘强,石立宝,倪以信,等.电力系统恢复控制的网络重构智能优化策略[J].中国电机工程学报,2009,29(13):8-15.Liu Qiang,Shi Libao,Ni Yixin,et al.Intelligent optimization strategy of the power grid reconfiguration during power system restoration[J].Proceedings of the CSEE,2009,29(13):8-15(in Chinese).
[9]
Wang Chong,Vittal V,Kolluri V S,et al.PTDF-based automatic restoration path selection[J].IEEE Trans. on Power Systems,2010,25(3):1686-1695.
[10]
刘强,石立宝,周明,等.电力系统恢复中机组恢复的优化选择方法[J].电工技术学报,2009,24(3):164-170.Liu Qiang,Shi Libao,Zhou Ming,et al.Optimal strategy for units-up during power system restoration[J].Transactions of China Electrotechnical Society,2009,24(3):164-170(in Chinese).
[11]
Sun Wei,Liu C C,Zhang Li.Optimal generator start-up strategy for bulk power system restoration[J].IEEE Trans. on Power Systems,2011,26(3):1357-1366.
[12]
Wang Chong,Vittal V,Sun Kai.OBDD-based sectionalizing strategies for parallel power system restoration[J].IEEE Trans. on Power Systems,2011,26(3):1426-1433.
[13]
Liu Yan,Gu Xueping.Skeleton-network reconfiguration based on topological characteristics of scale-free networks and discrete particle swarm optimization[J].IEEE Trans. on Power Systems,2007,22(3):1267-1274.
[14]
魏智博,刘艳,顾雪平.基于DPSO算法以负荷恢复为目标的网络重构[J].电力系统自动化,2007,31(1):38-42.Wei Zhibo,Liu Yan,Gu Xueping.DPSO algorithm based network reconfiguration of power systems for maximizing load recovery efficiency[J].Automation of Electric Power Systems,2007,31(1):38-42(in Chinese).
[15]
顾雪平,韩忠晖,梁海平.电力系统大停电后系统分区恢复的优化算法[J].中国电机工程学报,2009,29(10):41-46.Gu Xueping,Han Zhonghui,Liang Haiping.Optimization of parallel restoration through power system partitioning after blackout[J].Proceedings of the CSEE,2009,29(10):41-46(in Chinese).
[16]
王洪涛,刘玉田.基于NSGA-II的多目标输电网架最优重构[J].电力系统自动化,2009,33(23):14-18.Wang Hongtao,Liu Yutian.Multi-objective optimization of power system reconstruction based on NSGA-II[J].Automation of Electric Power Systems,2009,33(23):14-18(in Chinese).
[17]
刘艳,张凡,顾雪平.大停电后的机组投运风险评估[J].中国电机工程学报,2013,33(31):106-113.Liu Yan,Zhang Fan,Gu Xueping.Risk assessment for restoring units following large-scale blackout[J].Proceedings of the CSEE,2013,33(31):106-113(in Chinese).
[18]
刘艳,王涛,王文炎.用于网架重构方案运行风险评估的线路投运模型[J].中国电机工程学报,2014,34(7):1124-1131.Liu Yan,Wang Tao,Wang Wenyan.Model of restoring transmission lines for operational risk assessment of network-reconfiguration scheme[J].Proceedings of the CSEE,2014,34(7):1124-1131(in Chinese).
[19]
Ye Hua,Liu Yutian.A new method for standing phase angle reduction in system restoration by incorporating load pickup as a control means.International Journal of Electric Power and Energy Systems,2013,53:664-674.
[20]
王洪涛,刘玉田.电力系统恢复的主从递阶决策模型及其优化算法[J].中国电机工程学报,2007,27(1):8-13.Wang Hongtao,Liu Yutian.Leader-follower hierarchical decision model and optimal method for power system restoration[J].Proceedings of the CSEE,2007,27(1):8-13(in Chinese).
[21]
Feltes J,Grande-Moran C.Down,but not out:a brief overview of restoration issues[J].IEEE Power and Energy Magazine,2014,12(1):34-43.
[22]
谢广润.电力系统过电压[M].北京:水利电力出版社,1985.Xie Guangrun.Power system overvoltage[M].Beijing:Water&Power Press,1985(in Chinese).
[23]
王尔智,赵玉环.电力网络灵敏度分析与潮流计算[M].北京:机械工业出版社,1992.Wang Erzhi,Zhao Yuhuan.Power network sensitivity analysis and power flow calculation[M].Beijing:China Machine Press,1992(in Chinese).
[24]
Deb K,Pratap A,Agarwal S,et al.A fast and elitist multiobjective genetic algorithm:NSGA-II[J].IEEE Trans. on Evolutionary Computation,2002,6(2):182-197.
[25]
瞿寒冰,刘玉田.机组启动过程中的负荷恢复优化[J].电力系统自动化,2011,35(8):16-21.Qu Hanbing,Liu Yutian.Load restoration optimization during unit start-up stage[J].Automation of Electric Power Systems,2011,35(8):16-21(in Chinese).