考虑风电不确定性的机组检修鲁棒优化方法

DOI: 10.13334/j.0258-8013.pcsee.2015.12.001, PP. 2919-2926

Keywords: 检修计划,风电,鲁棒优化,不确定性集合,保守性

Full-Text   Cite this paper   Add to My Lib

Abstract:

大规模风电接入电网给传统电力系统机组检修决策问题带来了新的挑战,如何在历史统计数据不足的情况下考虑风电对机组检修的影响成为难点之一。将鲁棒优化理论引入检修决策领域,构建机组检修鲁棒优化模型,并给出风电不确定集合的构造方法。模型以风电最恶劣情景下系统运行最优为优化目标,保证系统运行安全性,通过调整不确定集合边界,可控制鲁棒优化模型的保守性,实现决策的经济性与安全性平衡。算例对比证明所提模型和方法在计算效率和计算结果中的优势。通过调整保守性参数,鲁棒优化模型可获得比传统随机规划模型更优的结果。

References

[1]  Cassady C R,Kutanoglu E.Integrating preventive maintenance planning and production scheduling for a single machine[J].IEEE Trans. on Reliability,2005,54(2):304-309.
[2]  Heo J H,Kim M K,Park G P,et al.A reliability-centered approach to an optimal maintenance strategy in transmission systems using a genetic algorithm[J].IEEE Trans. on Power Delivery,2011,26(4):2171-2179.
[3]  Hadji M M,Vahidi B.A solution to the unit commitment problem using imperialistic competition algorithm[J].IEEE Trans. on Power Systems,2012,27(1):117-124.
[4]  Camci F.System maintenance scheduling with prognostics information using genetic algorithm[J].IEEE Trans. on Reliability,2009,58(3):539-552.
[5]  Nourelfath M,Fitouhi M C,Machani M.An integrated model for production and preventive maintenance planning in multi-state systems[J].IEEE Trans. on Reliability,2010,59(3):496-506.
[6]  Burke E K,Smith A J.Hybrid evolutionary techniques for the maintenance scheduling problem[J].IEEE Trans. on Power Systems,2000,15(1):122-128.
[7]  陈少华,杨澎,周永旺,等.遗传和模拟退火算法在发电机组检修计划中的应用[J].电力系统自动化,1998,22(7):44-46.Chen Shaohua,Yang Peng,Zhou Yongwang,et al.A method combining genetic algorithm with simulated annealing approach for thermal unit maintenance scheduling[J].Automation of Electric Power Systems,1998,22(7):44-46(in Chinese).
[8]  Pandzic H,Conejo A J,Kuzle I,et al.Yearly maintenance scheduling of transmission lines within a market environment[J].IEEE Trans. on Power Systems,2012,27(1):407-415.
[9]  Wu Lei,Shahidehpour M,Li Tao.GENCO's risk-based maintenance outage scheduling[J].IEEE Trans. on Power Systems,2008,23(1):127-136.
[10]  Wu Lei,Shahidehpour M,Fu Yong.Security-constrained generation and transmission outage scheduling with uncertainties[J].IEEE Trans. on Power Systems,2010,25(3):1674-1685.
[11]  Silva E L,Schilling M T,Rafael M C.Generation maintenance scheduling considering transmission constraints[J].IEEE Trans. on Power Systems,2000,15(2):838-843.
[12]  Marwali M K C,Shahidehpour S M.Integrated generation and transmission maintenance scheduling with network constraints[J].IEEE Trans. on Power Systems,1998,13(3):1063-1068.
[13]  Fu Yong,Shahidehpour M,Li Zuyi.Security-constrained unit commitment with AC constraints[J].IEEE Trans. on Power Systems,2005,20(3):1538-1550.
[14]  Fu Yong,Shahidehpour M,Li Zuyi.Security-constrained optimal coordination of generation and transmission maintenance outage scheduling[J].IEEE Trans. on Power Systems,2007,22(3):1302-1313.
[15]  Khodaei A,Shahidehpour M.Transmission switching in security-constrained unit commitment[J].IEEE Trans. on Power Systems,2010,25(4):1937-1945.
[16]  张宁,周天睿,段长刚,等.大规模风电场接入对电力系统调峰的影响[J].电网技术,2010,34(1):152-158.Zhang Ning,Zhou Tianrui,Duan Changgang,et al.Impact of large-scale wind farm connecting with power grid on peak load regulation demand[J].Power System Technology,2010,34(1):152-158(in Chinese).
[17]  鲍爱霞.大规模风电场容量可信度的分析及对华东电网备用的影响[J].中国电机工程学报,2009,29(增刊):34-38.Bao Aixia.Analysis and research for capacity credit of large scale wind farms and influence on reserve capacity of east China electric power grid[J].Proceedings of the CSEE,2009,29(Supplement):34-38(in Chinese).
[18]  张宏宇,印永华,申洪,等.考虑大规模风电调峰要求的系统机组检修计划[J].电力系统自动化,2012,36(16):25-30.Zhang Hongyu,Yin Yonghua,Shen Hong,et al.Generator maintenance scheduling of large-scale wind power integration considering peak shaving[J].Automation of Electric Power Systems,2012,36(16):25-30(in Chinese).
[19]  吴耀武,邴焕帅,娄素华.含风电场的电力系统中考虑调峰压力平衡的机组检修规划模型[J].电网技术,2012,36(11):94-100.Wu Yaowu,Bing Huanshuai,Lou Suhua.A unit maintenance scheduling model considering peak regulation pressure balance for power system containing wind farms[J].Power System Technology,2012,36(11):94-100(in Chinese).
[20]  方陈,夏清,孙欣.考虑大规模风电接入的发电机组检修计划[J].电力系统自动化,2010,34(19):20-24.Fang Chen,Xia Qing,Sun Xin.Generation maintenance scheduling with significant wind power penetration[J].Automation of Electric Power Systems,2010,34(19):20-24(in Chinese).
[21]  Ben-Tal A,Ghaoui L E,Nemirovski A.Robus optimization[M].Princeton Series in Applied Mathematics.Princeton,NJ:Princeton University Press,2009.
[22]  Wu Wenchuan,Chen Jianhua,Zhang Boming,et al.A robust wind power optimization method for look-ahead dispatch[J].IEEE Transaction on Sustainable Energy,2014,5(2):507-515.
[23]  陈建华,吴文传,张伯明,等.安全性与经济性协调的鲁棒区间风电调度方法[J].中国电机工程学报,2014,34(7):1033-1040.Chen Jianhua,Wu Wenchuan,Zhang Boming,et al.A robust interval wind power dispatch method considering the tradeoff between security and economics[J].Proceedings of the CSEE,2014,34(7):1033-1040(in Chinese).
[24]  Dimitris B,Eugene L,Sun Xu Andy,et al.Adaptive robust optimization for the security constrained unit commiment problem[J].IEEE Transaction on Power Systems,2013,28(1):52-63.
[25]  Zeng Bo,Zhao Long.Solving two-stage robust optimization problems using a column-and-constraint generation method[J].Operations Research Letters,2013,41(5):457-61.
[26]  Bertsimas D,Sim M.The price of robustness[J].Operations Research,2004,52(1):35-53.
[27]  Wolsey L.Integer Programming[M].New York:Wiley Inter-Science,1998.
[28]  魏韡,刘锋,梅生伟.电力系统鲁棒经济调度(一)理论基础[J].电力系统自动化,2013,37(17):37-43.Wei Wei,Liu Feng,Mei Shengwei.Robust and economical scheduling methodology for power systems (Part One) theoretical foundations[J].Automation of Electric Power Systems,2013,37(17):37-43(in Chinese).
[29]  IEEE RTS Task Force of APM Subcommittee.IEEE reliability test system[J].IEEE Transactions on Power Apparatus and Systems,1979,PAS-98(6):2047-2054.
[30]  Doquet M.Use of a stochastic process to sample wind power curves in planning studies[C]//2007 IEEE Lausanne Power Technology,2007:663-670.

Full-Text

Contact Us

service@oalib.com

QQ:3279437679

WhatsApp +8615387084133