Engineering  2013 

Development of Highly Efficient Construction Technologies for Super Long Span Bridge

DOI: 10.4236/eng.2013.58075, PP. 629-636

Keywords: AS Equipment, PPWS Equipment, Slip Form System, Large Scale Foundation

Full-Text   Cite this paper   Add to My Lib

Abstract:

This paper presents highly efficient cable erection equipments and methods related to the construction of super-long-span bridges, construction technology of high towers and, technology for offshore foundations currently developed through a R&D on accelerated and cost-saving construction technology for long-span cable bridges to secure our international competitiveness. In the field of cable erection technology, AS and PPWS equipments for highly efficient erection of cable longer than 2000 m, world-class clamping bolt tensioning equipment and shape control system for super-long cable are under development. The technologies developed in the domain of construction of towers are tapered slip form system for the construction of 400 m high tower, shape and erection precision control of elevated tower and, lightweight and modular formwork for slip form system. In the domain of foundation construction, remote controlled survey equipment and analysis system for water-depth of 100 m and depth of 50 m, prediction and evaluation technology of optimal load carrying capacity and settlement complying with international standard and, highly efficient hybrid foundation construction technology suitable for ground acceleration of 0.5 g and deep soft soil are currently developed.

References

[1]  Korea Institute of Construction & Transportation Tech nology Evaluation and Planning, “Detailed Planning Study for Super-Long-Span Bridge R&BD Project,” 2008.
[2]  H. S. Choi and J. H. Kim, “Construction Method of Main Cable for Suspension Bridges,” Magazine and Journal of Korean Society of Steel Construction, Vol. 20, No. 2, 2008, pp. 79-86.
[3]  M. J. Ryall, G. A. R. Parke and J. E. Harding, “The Man ual of Bridge Engineering,” Thomas Telford Ltd., 2000.
[4]  Y. Yasutsugu and F. Rouvillain, “Cable Construction of the Great Belt East Bridge,” Foundation of Bridge, Vol. 97, No. 5, 1997, pp. 15-22.
[5]  J. H. Moon and S. P. Chang, “Shape Adjustment of the Main-Cable of Suspension Bridges,” Magazine and Jour nal of Korean Society of Steel Construction, Vol. 20, No. 2, 2008, pp. 47-53.
[6]  Jinsung Construction Co. Ltd., “Erection and Quality Control Using Slip-Form System,” 2009.
[7]  D. Thomas, “Slipform Works for Pylons—Machang Bridge,” GBG.

Full-Text

Contact Us

service@oalib.com

QQ:3279437679

WhatsApp +8615387084133