Utilising Best Practice in Project Planning and Scheduling for Capital Projects Success: Assessing the Importance of a Botswana Mining Company’s Strategy-Sensitive Capital Projects
The purpose of this study was to quantitatively assess the importance of employing best practices in project planning and scheduling on capital projects’ success in Botswana, using a mining company’s strategy-critical projects as a case study. Seventy-two (72) respondents who are employees of the mining company completed the questionnaire. The study purposefully selected a convenient sample of individuals involved in managing capital projects. Data was collected using a closed-ended questionnaire utilizing Google forms. The same data was analysed using descriptive statistics, ANOVA statistics, collinearity statistics, multiple regression and inferential analysis formed part of the statistics used with the aid of IBM SPSS Version 25. The results of multiple linear regression revealed that out of the three factors investigated, project planning and front-end planning are significant predictors of capital project success, while project scheduling techniques are not significant predictors of project success of capital projects at the mining company. Based on the findings derived from statistical analysis, the study concluded that project planning best practices have benefited capital projects at the mining company, although with a moderately high success rate. The study recommends that the mining company’s project team should be critical in selecting and applying the appropriate scheduling techniques that can enable effective monitoring and control of project tasks. In addition to this, more studies should be conducted focusing on a broader scope of the application of scheduling techniques on capital projects’ success.
Cite this paper
Baleni, P. and Gande, T. (2023). Utilising Best Practice in Project Planning and Scheduling for Capital Projects Success: Assessing the Importance of a Botswana Mining Company’s Strategy-Sensitive Capital Projects. Open Access Library Journal, 10, e304. doi: http://dx.doi.org/10.4236/oalib.1110304.
Kagogo, T.S. and Steyn, H. (2019) Effect of Scope Readiness on Capital Projects in Mining. South African Journal of Industrial Engineering, 30, 257-269.
Asare, K.A.B., Liu. R. and Anumba, C.J. (2022) Building Information Modeling to Support Facilities Management of Large Capital Projects: A Critical Review. Facilities, 40, 176-197. https://doi.org/10.1108/F-11-2020-0124
Ogbeifun, E. and Pretorius, J.H.C. (2022) Ameliorating the Effects of Time Overrun in the Execution of Capital Infrastructure Projects. Proceedings of the International Conference on Industrial Engineering and Operations Management, Nsukka, 5-7 April 2022, 303-314.
Choi, J.O., Shrestha, B.K., Kwak, Y.H. and Shane, J. (2022) Exploring the Benefits and Trade-Offs of Design Standardization in Capital Projects. Engineering, Construction and Architectural Management, 29, 1169-1193.
https://doi.org/10.1108/ECAM-08-2020-0661
Mutoko, W.R. and Mutoko, P. (2019) Literature Review on the Solar Energy Potential for Botswana. European Scientific Journal, 15, 27-43.
https://doi.org/10.19044/esj.2019.v15n34p27
AlNasseri, H.A. (2015) Understanding Applications of Project Planning and Scheduling in Construction Projects. Division of Construction Management, Department of Construction Sciences, Faculty of Engineering, Lund University, Riyadh.
Kafile, M. (2021) Project Planning and Scheduling in the Face of the Fourth Industrial nd Scheduling in the Face of the Fourth Industrial. Journal of Business Administration Research, 4, 51-61. https://doi.org/10.30564/jbar.v4i3.3398
Gaur, S. (2022) Understanding the Importance of Project Planning and Scheduling in Indian Construction Projects. Journal of Positive School Psychology, 6, 3535-3544.
Agyemang, O.O. (2021) Assessing the Relationship between Project Planning Effort and Project Successin the Construction Indudtry of Ghana. International Journal of Research Publication and Reviews, 2, 373-386.
Akinradewo, O., Aigbavboa, C. and Akinradewo, O. (2019) Impact of Construction Project Planning on Contractor’s Profit. IOP Conference Series: Earth and Environmental Science, 385, Article ID: 012009.
https://doi.org/10.1088/1755-1315/385/1/012009
Al-Hazim, N., Salem, Z.A. and Ahmad, H. (2017) Delay and Cost Overrun in Infrastructure Projects in Jordan. Procedia Engineering, 182, 18-24.
https://doi.org/10.1016/j.proeng.2017.03.105
Segelod, E. (2017) Project Cost Overrun: Decision-Making, Overruns, and Their Consequences. Cambridge University Press, Cambridge.
https://doi.org/10.1017/9781316779675
Deshmukh, P. and Rajhans, N.R. (2018) Comparison of Project Scheduling Tecniques: PERT versus Monte Carlo Simulation. Industrial Engineering Journal, 11, 1-13.
Zareei, S. (2018) Project Scheduling for Constructing Biogas Plant Using Critical Path Method. Renewable and Sustainable Energy Reviews, 81, 756-759.
https://doi.org/10.1016/j.rser.2017.08.025
Ballesteros-Perez, P., Larsen, G.D. and Gonzealez-Cruz, M.C. (2018) Do Projects Really End Late? On the Shortcomings of the Classical Scheduling Techniques. Journal of Technology and Science Education, 8, 17-33.
https://doi.org/10.3926/jotse.303
Shikhrobat, M.B., Kabiri, S. and Flanagan, R. (2019) Project Planning and Scheduling using System Dynamics for Dealing with Complexity on Construction Projects., Proceedings of the 35th Annual ARCOM Coference, Leeds, 2-4 September 2019, 689-698.
Varsani, A.D., Bhavsar, P.A.N. and Pitroda, D.J.R. (2020) Effective Scheduling and Control of Construction Project Using Primavera P6: A Review. Studies in Indian Place Names (UGC Care Journal), 40, 5050-5064.
Gautam, G.P.S. and Paliwal, P.M.C. (2019) A Literature Review: Analysis of Different Projects for Timely Completion of Construction Projects. Research Journal of Science Engineering and Technology, 9, 38-41.
Franco-Duran, D.M. and de la Garza, J.M. (2019) Phantom Float in Commercial Scheduling Software. Automation in Construction, 103, 291-299.
https://doi.org/10.1016/j.autcon.2019.03.014
Bagade, P.P. and Bhirud, A. (2018) Review on Construction Project Management Software Primavera P6. International Journal of Engineering Sciences and Research Technology, 7, 110-114.
Sharma, C.K., Gohel, R.V., Chauhan, V.B. and Bhavsar, A.N. (2016) Study of MS Project Software and Its Application in Construction Project and Case Study at Anand. International Journal of Advanced Reseach and Innovative Ideas in Education (IJARIIE), 2, 2862-2870.
Gibson, E.G.J. and Stogner, E.B.R. (2010) Front End Planning for Infrastructure Projects. American Society of Civil Engineers, Alberta, 1125-1135.
https://doi.org/10.1061/41109(373)113
Williams, T.M., Samset, K. and Volden, G.H. (2022). The Front-End of Large Public Projects: Paradoxes and Ways Ahead. Taylor and Francis, London.
https://doi.org/10.4324/9781003257172
Samset, K. and Volden, G.H. (2016) Front-End Definition of Projects: Ten Paradoxes and Some Reflections Regarding Project Management and Project Governance. Interntaional Journal of Project Management, 34, 297-313.
https://doi.org/10.1016/j.ijproman.2015.01.014
Hwang, B.G. (2016) Does “Front-End Planning” Work for the Singapore Construction Industry? World Construction Conference 2012—Global Challenges in Construction Industry, 28-30 June 2012, Colombo, 162-170.
Turyahikayo, E. (2021) Philosophical Paradigms as the Bases for Knowledge Management Research and Practice. Knowledge Management and E-Learning, 13, 209-224. https://doi.org/10.34105/j.kmel.2021.13.012
Shareria, F.B. (2016) Quantitative and Qualitative Case Study Research Methods on Social Science: Accounting Perspective. International Journal of Economics and Management Engineering, 10, 3839-3844.
Thomas, B. (2022) The Role of Purposive Sampling Technique as a Tool for Informal Choices in a Social Sciences in Research Methods. Just Agriculture Multidisciplinary E-Newsletter, 2, Article ID: 047.
Tongco, D.C. (2007) Purposive Sampling as a Tool for Information Selection. Ethnobotany Research and Applications, 5, 146-158.
https://doi.org/10.17348/era.5.0.147-158
Surucu, L. and Maslakci, A. (2020) Validity and Reliability in Quantitative Research. Business and Management Studies: An International Journal, 8, 2694-2726.
https://doi.org/10.15295/bmij.v8i3.1540
Naeem, S., Khanzada, B., Mubashir, T. and Sohail, H. (2018) Impact of Project Planning on Project Success with Mediating Role of Risk Management and Moderating Role of Organizational Culture. International Journal of Business and Social Science, 9, 88-98.
Kartikeyan, G., Gholap, R., Katkar, R., Khune, P. and Bhosale, P. (2021) To Study Advanced Project Planning and Scheduling-Case Study. International Journal of Advance Scientific Research and Engineering Trends, 12, 286-297.
Hansen, S., Too, E. and Le, T. (2018) Retrospective Look on Front-End Planning in the Construction Industry: A Literature Review of 30 Years of Research. International Journal of Construction Supply Chain Management, 8, 19-42.