电网技术  2014 

计及分布式电源与电容器协调的配电网日前无功计划

DOI: 10.13335/j.1000-3673.pst.2014.09.043, PP. 2590-2597

Keywords: 配电网,分布式电源,日前无功计划,协调优化,模糊聚类

Full-Text   Cite this paper   Add to My Lib

Abstract:

针对目前含分布式电源(distributedgeneration,DG)的配电网中未考虑电容器补偿容量和DG无功出力协调调度的问题,研究了考虑DG与电容器组协调的无功优化方法。以网损和电压偏移满意度最高为目标,构建含DG的配电网日前动态无功优化调度模型。根据DG无功出力和电容器补偿的特点,提出DG和电容器协调的日前无功计划方法。分析了各类DG的无功出力极限并作为约束条件,对电容器和DG进行整体静态优化得到电容器的投切容量曲线;其次采用模糊聚类对电容器投切曲线进行时序分段并融合,制定电容器的日前计划;最后,在电容器补偿容量确定后,以DG作为优化变量,制定DG出力的日前计划。仿真结果验证了所提方法的有效性。

References

[1]  刘杨华,吴政球,涂有庆,等.分布式发电及其并网技术综述[J].电网技术,2008,32(15):71-75.
[2]  Liu Yanghua,Wu Zhengqiu,Tu Youqing,et al.A survey on distributed generation and its networking technology[J].Power System Technology,2008,32(15):71-75(in Chinese).
[3]  Augusto C,Medina R.Distributed generators as providers of reactive power support-a market approach[J].IEEE Trans on Power Systems,2013,28(1):490-502.
[4]  Wang Wei,Xu Lijie,Wang Shidan.Research on the reactive power optimization of distribution network including DG[C]//3rd IEEE International Symposium on Power Electronics for Distributed Generation Systems(PEDG).Tianjin:IEEE,2012:207-210.
[5]  Braun M.Reactive power supply by distributed generators[C]//2008 IEEE Power and Energy Society General Meeting.Pittsburgh,USA:IEEE,2008:1-8.
[6]  蔡昌春,丁晓群,王宽,等.动态无功优化的简化方法及实现[J].电力系统自动化,2008,32(5):43-46.
[7]  Cai Changchun,Ding Xiaoqun,Wang Kuan,et al.Simplified method of dynamic reactive power optimization and its implementation[J].Automation of Electric Power Systems,2008,32(5):43-46(in Chinese).
[8]  赵晶晶,符杨,李冬冬.考虑双馈电机风电场无功调节能力的配电网无功优化[J].电力系统自动化,2011,35(11):33-38.
[9]  Zhao Jingjing,Fu Yang,Li Dongdong.Reactive power optimization in distribution network considering reactive power regulation capability of DFIG wind farm[J].Automation of Electric Power Systems,2011,35(11):33-38(in Chinese).
[10]  石嘉川,刘玉田,计及分布式发电的配电网多目标电压优化控制[J].电力系统自动化,2007,31(13):47-51.
[11]  Shi Jiachuan,Liu Yutian.Multi-objective voltage control in distribution network with distributed generation[J].Automation of Electric Power Systems,2007,31(13):47-51(in Chinese).
[12]  李鸿鑫,李银红,李智欢.多目标进化算法求解无功优化问题的比较与评估[J].电网技术,2013,37(6):1651-1658.
[13]  Li Hongxin,Li Yinhong,Li Zhihuan.Research of reactive power optimization control in distribution networks based on genetic algorithm[J].Power System Technology,2013,37(6):1651-1658(in Chinese).
[14]  张庭场,耿光飞.基于改进粒子群算法的中压配电网无功优化[J].电网技术,2012,36(2):158-162.
[15]  Zhang Tingchang,Geng Guangfei.Reactive power optimization for medium voltage distribution network based on improved particle swarm optimization[J].Power System Technology,2012,36(2):158-162(in Chinese).
[16]  吴方劼,张承学,段志远.基于动态多种群粒子群算法的无功优化[J].电网技术,2007,31(24):35-39.
[17]  Wu Fangjie,Zhang Chengxue,Duan Zhiyuan.Application of modified particle swarm optimization in reactive power optimization11 [J].Power System Technology,2007,31(24):35-39(in Chinese).
[18]  曾令全,罗富宝,丁金嫚.禁忌搜索-粒子群算法在无功优化中的应用[J].电网技术,2011,35(7):129-133.
[19]  Zeng Lingquan,Luo Fubao,Ding Jinman.Application of particle swarm optimization algorithm integrated with tabu search in reactive power optimization[J].Power System Technology,2011,35(7):129-133(in Chinese).
[20]  李智,杨洪耕.考虑边界母线电压无功特性的地区电网无功优化[J].电网技术,2012,36(9):126-132.
[21]  Li Zhi,Yang Honggeng.Reactive power optimization of regional power grid considering voltage and reactive power characteristics of boundary buses[J].Power System Technology,2012,36(9):126-132(in Chinese).
[22]  郎永强,张学广,徐殿国,等.双馈电机风电场无功功率分析及控制策略[J].中国电机工程学报,2007,27(9):77-82.
[23]  Lang Yongqiang,Zhang Xueguang,Xu Dianguo,et al.Reactive power analysis and control of doubly fed induction generator wind farm[J].Proceedings of the CSEE,2007,27(9):77-82(in Chinese).
[24]  Zou K,Agalgaonkar A P,Muttaqi K M,et al.Distribution system planning with incorporating DG reactive capability and system uncertainties[J].Sustainable Energy,IEEE Transactions on Power System,2012,3(1):112-123.
[25]  李晓军,禹华军.多功能光伏并网发电技术研究[J].上海电气技术,2007(1):14-19.
[26]  Li Xiaojun,Yu Huajun.Research on multi-function grid-connected PV system[J].Journal of Shanghai Electric Technology,2007(1):14-19 (in Chinese).
[27]  杨秀,郭贤,臧海洋,等.微型燃气轮机发电系统孤岛及并网运行的建模与控制策略[J].电工技术学报,2012,27(1):63-68.
[28]  Yang Xiu,Guo Xian,Zang Haiyang,et al.Modeling and control strategy of islanding and grid-connected operation of a micro-turbine generation system[J].Transactions of China Electrotechnical Society,2012,27(1):63-68(in Chinese).
[29]  李培强,李欣然,陈辉华,等.基于模糊聚类的电力负荷特性的分类与综合[J].中国电机工程学报,2005,25(24):73-78.
[30]  Li Peiqiang,Li Xinran,Chen Huihua,et al.The characteristics classification and synthesis of power load based on fuzzy clustering[J].Proceedings of the CSEE,2005,25(24):73-78(in Chinese).
[31]  张璐,唐巍,丛鹏伟,等.基于机会约束规划和二层规划的配电网广义电源优化配置[J].电力系统自动化,2014,38(5):50-58.
[32]  Zhang Lu,Tang Wei,Cong Pengwei,et al.Optimal configuration of generalized power sources in distribution network based on chance constrained programming and bi-level programming[J].Automation of Electric Power Systems,2014,38(5):50-58(in Chinese).

Full-Text

Contact Us

service@oalib.com

QQ:3279437679

WhatsApp +8615387084133