汇集站和集群中心站分级协调的风场群接入系统优化规划

DOI: 10.13334/j.0258-8013.pcsee.2014.S.001, PP. 1-8

Keywords: 风电场集群,协调规划,风电传输,容量优化,风电场分组,遗传算法

Full-Text   Cite this paper   Add to My Lib

Abstract:

风电消纳难题的根源在于风电与电网规划的不协调,单个风电场的接入系统各自依据其边界条件设计,叠加得到风电场集群的区域接入电网往往难以达到最优效果,甚至是不可行方案。该文提出风电场集群的接入系统协调规划模型,以经济性最优为目标,对接入系统进行汇集站及集群中心站两级综合协调优化。模型考虑风电送出受阻电量的损失、风电送出电量的效益、风电场集群内部升压变电站选址、各个风电场接入线路容量以及风电场集群分组等因素,并利用遗传算法对上述综合协调模型双层分解后进行优化求解,最后通过算例验证了模型和方法的有效性。

References

[1]  张粒子,凡鹏飞,麻秀范,等.考虑调峰适应性风险的风电场群时序规划方法[J].中国电机工程学报,2012,32(7):14-22. Zhang Lizi,Fan Pengfei,Ma Xiufan,et al.Timing planning method for investmentof clustering wind farms considering risk of peak load regulation[J].Proceedings of the CSEE,2012,32(7):14-22(in Chinese).
[2]  Gonzalez-Longatt F M,Wall P,Regulski P,et al.Optimal electric network design for a large offshore wind farm based on a modified genetic algorithm approach[J].IEEE Systems Journal,2012,6(1):164-172.
[3]  Elliott D W,Jones C E,Finney S J.Offshore wind farm cluster based DC collection network &—Operation and design considerations[C]//10th IET International Conference on AC and DC Power Transmission.Birmingham:IET,2012:1-6.
[4]  中国可再生能源学会风能专业委员会.2013年中国风电装机容量统计[R].北京:中国可再生能源学会,2014. Chinese Wind Energy Association.China installed wind power capacity in 2013[R].Beijing:China Renewable Energy Society,2014(in Chinese)
[5]  Kamalinia S,Shahidehpour M.Generation expansion planning in wind-thermal power systems[J].IET Generation,Transmission & Distribution,2010,4(8):940-951.
[6]  Mun X,Oz C,Sauma E,et al.Impact of high wind power penetration on transmission network expansion planning[J].IET Generation,Transmission & Distribution,2012,6(12):1281-1291.
[7]  Billinton R,Wangdee W.Reliability-based transmission reinforcement planning associated with large-scale wind farms[J].IEEE Transactions on Power Systems,2007,22(1):34-41.
[8]  Moeini-Aghtaie M,Abbaspour A,Fotuhi-Firuzabad M.Incorporating large-scale distant wind farms in probabilistic transmission expansion planning part I:Theory and algorithm[J].IEEE Transactions on Power Systems,2012,27(3):1585-1593.
[9]  Moeini-Aghtaie M,Abbaspour A,Fotuhi-Firuzabad M.Incorporating large-scale distant wind farms in probabilistic transmission expansion planning part II: Case studies[J].IEEE Transactions on Power Systems,2012,27(3):1594-1601.
[10]  Yu H,Chung C Y,Wong K P,et al.A chance constrained transmission network expansion planning method with consideration of load and wind farm uncertainties [J].IEEE Transactions on Power Systems,2009,24(3):1568-1576.
[11]  乔嘉赓,徐飞,鲁宗相,等.基于相关机会规划的风电并网容量优化分析[J].电力系统自动化,2008,32(10): 84-103. Qiao Jiageng,Xu Fei,Lu Zongxiang,et al.Optimal analysis model of grid-connected wind capacity based on dependent chance programming[J].Automation of Electric Power Systems,2008,32(10):84-103(in Chinese).
[12]  Orfanos G A,Georgilakis P,Hatziargyriou N D.Transmission expansion planning of systems with increasing wind power integration[J].IEEE Transactions on Power Systems,2013,28(2):1355-1362.
[13]  Mori H,Kakuta H.Multi-objective transmission network expansion planning in consideration of wind farms [C]//2011 2nd IEEE PES International Conference and Exhibition on Innovative Smart Grid Technologies (ISGT Europe).Manchester:IEEE,2011:1-7.
[14]  王茜,张粒子.采用NSGA-Ⅱ混合智能算法的风电场多目标电网规划[J].中国电机工程学报,2011,31(19):17-24. Wang Qian,Zhang Lizi.Multi-objective transmission planning associated with wind farms applying NSGA-Ⅱ hybrid intelligent algorithm[J].Proceedings of the CSEE,2011,31(19):17-24(in Chinese).
[15]  刘燕华,田茹,张东英,等.风电出力平滑效应的分析与应用[J].电网技术,2013,37(4):987-991. Liu Yanhua,Tian Ru,Zhang Dongying,et al.Analysis and application of wind farm output smoothing effect[J].Power System Technology,2013,37(4):987-991(in Chinese).
[16]  肖创英,汪宁渤,陟晶,等.甘肃酒泉风电出力特性分析[J].电力系统自动化,2010,34(17): 64-67. Xiao Chuangying,Wang Ningbo,Zhi Jing,et al.Power characteristics of Jiuquan wind power base[J].Automation of Electric Power Systems,2010,34(17):64-67(in Chinese).
[17]  穆钢,崔杨,严干贵.确定风电场群功率汇聚外送输电容量的静态综合优化方法[J].中国电机工程学报,2011,31(1): 15-19. Mu Gang,Cui Yang,Yan Gangui.A static optimization method to determine integrated power transmission capacity of clustering wind farms[J].Proceedings of the CSEE,2011,31(1):15-19(in Chinese).