%0 Journal Article
%T DEMOLITION OF ZHANGZE WORKSHOPS OF A POWER PLANT IN SHANXI PROVINCE THROUGH CONTROLLED BLASTING
山西漳泽电厂厂房控制爆破拆除
%A ZHANG Yingcai
%A
张英才
%J 力学与实践
%D 2006
%I
%X In view of the complex environment of demolision project of Zhangze power plant workshops in Shanxi province and the workshop's actual structure, we divide the workshop into three explosion areas and determine the overall directional demolition plan with one explosive initiation point, 12 sound elemental difference delays, and a non-electrically strengthened dual-loop demolition network. The demolition vibration is calculated and verified. Effective measures are taken to reduce the cave in distance. Good blasting results are obtained.
%K blasting demolition
%K the elemental difference postpones
%K blasting network
爆破拆除
%K 微差延期
%K 爆破网路
%U http://www.alljournals.cn/get_abstract_url.aspx?pcid=6E709DC38FA1D09A4B578DD0906875B5B44D4D294832BB8E&cid=5D344E2AD54D14F8&jid=0BF5C9FB031A532ED0A6D99DC4F6181A&aid=79358C79BF236778&yid=37904DC365DD7266&vid=D3E34374A0D77D7F&iid=CA4FD0336C81A37A&sid=CB423C9A71560A74&eid=B9704B40A4225A24&journal_id=1000-0879&journal_name=力学与实践&referenced_num=4&reference_num=4