Risk Analysis of Integrated Pipe Gallery PPP Project Based on the Analytic Hierarchy Process

DOI: 10.4236/oalib.1105680, PP. 1-10

Subject Areas: Risk Management

Keywords: Risk Analysis, PPP Project, Analytic Hierarchy Process

Full-Text   Cite this paper   Add to My Lib

Abstract

As a public infrastructure for integrated construction, the integrated pipe corri-dor can extend the service life of the road and save the urban ground space [1]. Rational distribution of integrated pipe corridors provides a strong guarantee for the sustainable development of the city [2]. In recent years, the integrated management of the corridor government and social capital cooperation (PPP) has been widely used in China, in the integrated pipe gallery PPP project, high-speed under the development situation, problems such as out-of-control design in the early stage and loss of trust during the construction period are frequent. Contractual disputes caused by these problems, government repurchase, project suspension and other risks damage the project benefits, which seriously violate the original intention of the project [3]. PPP projects are characterised by long-term, variability and complexity. Risks are more difficult to control than conventional projects. It is a need for a dynamic risk management system that can effectively prevent and control the occurrence of risks, accurately assess risk factors and ensure the protection of risk management.

Cite this paper

Yue, Y. , Wu, J. , Liu, S. and Zhang, Y. (2019). Risk Analysis of Integrated Pipe Gallery PPP Project Based on the Analytic Hierarchy Process. Open Access Library Journal, 6, e5680. doi: http://dx.doi.org/10.4236/oalib.1105680.

References

[1]  Fan, H., Wang, F. and Wang, G.W. (2017) Research Progress in the Laying Method of Hot Water Hot Pipe Gallery. Journal of Huaqiao University (Natural Science), 38, 747-752.
[2]  Wang, Y. and Fu, Z.L. (2013) Research on the Countermeasures of Urban Comprehensive Pipeline Charging Based on Game Analysis. Chinese Journal of Under-ground Space and Engineering, 9, 197-203.
[3]  Xue, M. and Liu, H.M. (2011) Study on the Improvement of Post-Evaluation System of Government Investment Projects in China. Journal of Engineering Management, 25, 318-322.
[4]  Wang, L.C. (2016) Analysis of Several Key Issues in the Promotion of PPP Mode in China at the Present Stage. Friends of Accounting, 6, 2-7.
[5]  Wang, S.Q. (2016) Research on Professional Ethics Requirements in the Implementation of PPP Projects. Building Economy, 37, 37-41.
[6]  Li, H. (2014) A Review of Risk Management Research in PPP Projects. Building Economy, 35, 37-41.
[7]  Zhang, L. (2015) Risk Analysis of PPP Mode. Master’s Thesis of the Ministry of Finance, Beijing.
[8]  Saaty, T.L. (2000) Fundamentals of Decision Making and Priority Theory with the Analytic Hierarchy Process. In: Schmoldt, D.L., Kangas, J., Mendoza, G.A. and Pesonen, M., Eds., The Analytic Hierarchy Process in Natural Resource and En-vironmental Decision Making, Springer, Berlin, 15-35.
https://doi.org/10.1007/978-94-015-9799-9_2